Planning and Statistics Authority
Project charter
Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate
1Project identity
Required at this stage- Project name
- Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate
- Project code
- PRJ-2026-034
- Project sponsor
- Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.sy
- Project manager
- Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy
- Project owner
- Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy
- Portfolio & programme
- Reconstruction & Infrastructure PortfolioDamaged Areas Reconstruction Programme
- Type & methodology
- Infrastructure · Construction
- Current phase
- 4Execution
2Background & rationale
Required at this stageRehabilitating roads, water and drainage networks and street lighting in Maarat al-Numan with Idlib Governorate, so residents and public services can return.
3Objectives
Required at this stage- 1Rebuild damaged areas and provide replacement housing
- 2Comparable public-service quality in every governorate
4Scope
Required at this stageIn scope
- Rehabilitating roads, water and drainage networks and street lighting in Maarat al-Numan with Idlib Governorate, so residents and public services can return.
- Syrian Arab Building Code compliance
- An approved plan to keep services running for residents during the works
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
5High-level requirements
Required at this stage- 1Syrian Arab Building Code compliance
- 2An approved plan to keep services running for residents during the works
- 3Civil-defence requirements
6Deliverables
Required at this stage| 1 | Project management plan | 2025-08-06 |
| 2 | Main deliverable — stage 1 | 2026-08-11 |
| 3 | Main deliverable — final stage | 2027-05-13 |
| 4 | Final report | 2027-08-31 |
7Key milestones
Required at this stage- Charter approved2025-07-04
- Contract signed2025-11-09
- 50% of works complete2026-08-11
- Provisional acceptance2027-06-29
- Closure2027-08-31
8Budget
Required at this stage- Main contract72.0%SYP4.3B
- Supervision & consulting14.0%SYP832.5M
- Internal team9.0%SYP535M
- Contingency reserve (5%)5.0%SYP297.5M
9Timeline
Required at this stage10Key risks
Required at this stage- HighCity council late clearing rubble and opening access roads to the work sites
11Constraints
Required at this stage- Stay within the approved budget
- Comply with the unified contracts law (Law 51 of 2004)
12Assumptions
Required at this stage- Named internal staff available throughout
- Approvals land within the workflow’s action time limits
13Stakeholders
Required at this stage- Project sponsorDecisions and funding
- Project ownerAccepts deliverables, owns benefits
- National Project Management Office (PMO)Governance and compliance
14Success criteria
Required at this stage- 1Delivered within the approved budget
- 2On the approved date ±5%
- 3Target benefits within 12 months
15Governance structure
Required at this stage- Change CommitteeApproves scope, cost and schedule changesWeekly
- Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
- Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly