PRJ-2026-034At risk4ExecutionConstructionIn progressDelivered by:Ministry of Public Works and Housing
Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate
Add to watchlistRehabilitating roads, water and drainage networks and street lighting in Maarat al-Numan with Idlib Governorate, so residents and public services can return.
Project managerEng. Wael Al-KhawlaniProject sponsorEng. Abdulrahman Al-KilaniProgrammeDamaged Areas Reconstruction Programme
Early warning: 55% chance of slipping within 60 days
Budget (BAC)
SYP 6B
Actual cost
SYP 2B
34% of budget
Progress
33%Awaiting acceptance 12%
Estimate at completion
SYP 6.2B
+SYP 247.9M
SPI · CPI
0.89Schedule performance index · 0.890.96Cost performance index · 0.96
Forecast finish
2027-09-28
28 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure29 June 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started