Original
Original baseline
- Finish
- 2027-08-31
- Budget
- SYP 6B
- 17 activities
Approved with the project plan at the planning gate.
Approved 2025-07-06 · by Eng. Abdulrahman Al-Kilani
Rehabilitating roads, water and drainage networks and street lighting in Maarat al-Numan with Idlib Governorate, so residents and public services can return.
Budget (BAC)
Actual cost
34% of budget
Progress
Estimate at completion
+SYP 247.9M
SPI · CPI
Forecast finish
28 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure29 June 2027
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-07-06 · by Eng. Abdulrahman Al-Kilani
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Wael Al-Khawlani
What changed from version A to version B
Finish
2027-08-312027-09-27
+27 days
Budget
SYP 6BSYP 6B
0.00 SYP M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SYP millions from A to B
Every saved version with its reason and reference