Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate
Add to watchlistRehabilitating roads, water and drainage networks and street lighting in Maarat al-Numan with Idlib Governorate, so residents and public services can return.
Budget (BAC)
Actual cost
34% of budget
Progress
Estimate at completion
+SYP 247.9M
SPI · CPI
Forecast finish
28 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure29 June 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started
Team & roles
2 members, about 1.3 full-time equivalents
Leadership
1 member
- Eng. Wael Al-KhawlaniProject manager70%A
Vendor team & advisers
1 member
- Eng. Adnan Al-MohammadSite engineer60%R
A AccountableR ResponsibleC ConsultedI Informed
Stakeholders
6 stakeholders, 5 of them below the engagement needed
Power / interest matrix
Pick one to see how they are handled
Keep satisfied1
high power, lower interest
Manage closely4
high power and interest
Monitor0
minimal effort
Keep informed1
high interest, lower power
Interest
Project sponsor
Eng. Abdulrahman Al-Kilani
Decisions and funding
Influence
Interest
Engagement level
Unaware
Resistant
Neutral
Supportive
Leading
A gap of 1 step — needs an engagement plan.
- Impact on the project
- Approves gates and changes
- Engagement plan
- Monthly briefing
Display options
| Organisation | Role | Actions | ||||||
|---|---|---|---|---|---|---|---|---|
| Eng. Abdulrahman Al-Kilani | Project sponsor | Decisions and funding | SupportiveLeading | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | 2026-08-27 | |||
| Eng. Fadi Al-Droubi | Project owner | Accepts deliverables, owns benefits | SupportiveLeading | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | 2026-08-30 | |||
| Project Management Office (PMO) | Governance | Compliance and data quality | Supportive | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | 2026-08-24 | |||
| General Directorate of Financial Affairs | Internal department | Payment approval | NeutralSupportive | Huda Al-DandalHuda Al-DandalSenior Financial Analyst — Investment PlanP-037huda.aldandal@psa.gov.sy | 2026-08-21 | |||
| Al-Bunyan Al-Mateen Contracting Co. | Main vendor | Delivers the contracted work | ResistantSupportive | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | 2026-08-31 | |||
| End beneficiaries | Beneficiaries | Users of the outcome | NeutralSupportive | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | 2026-08-03 |
Communication plan
Who needs what, when, through which channel, and who owns it.
- Project sponsorStatus and decisions neededMonthlyMeetingEng. Wael Al-Khawlani2026-09-22
- Project ownerDeliverable status and acceptance datesFortnightlyEmailEng. Wael Al-Khawlani2026-09-10
- PMOData and indicator updatesWeeklyDashboardEng. Wael Al-Khawlani2026-09-07
- BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Wael Al-KhawlaniAt launch
Coming up
By date
- 072026-09PMODashboard · Weekly
- 102026-09Project ownerEmail · Fortnightly
- 222026-09Project sponsorMeeting · Monthly