Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate
Add to watchlistRehabilitating roads, water and drainage networks and street lighting in Maarat al-Numan with Idlib Governorate, so residents and public services can return.
Budget (BAC)
Actual cost
34% of budget
Progress
Estimate at completion
+SYP 247.9M
SPI · CPI
Forecast finish
28 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure29 June 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-12-15 | 2026-02-14 | +61 days | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-04-19 | 2026-08-04 | +107 days | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-10-23 | 2027-03-01 | +129 days | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-04-28 | 2027-07-05 | +68 days | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-08-31 | 2027-09-27 | +27 days | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
33%Awaiting acceptance
12%Not handed in
55%Deliverable flow
Display options
| Project plan & baseline034-D1 | 3% | CRT-034-01 | Approved | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | Eng. Fadi Al-Droubi | 2025-10-14 | V1 | 3 of 3 |
| Monitoring & reporting034-D2 | 3% | CRT-034-02 | Approved | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2025-12-15 | V1 | 3 of 3 |
| Detailed design034-D3 | 7% | CRT-034-03 | Approved | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-02-16 | V1 | 3 of 3 |
| Permits & approvals034-D4 | 6% | CRT-034-04 | Approved | Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-04-19 | V1 | 3 of 3 |
| Site works & excavation034-D5 | 14% | CRT-034-05 | Approved | Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-06-20 | V1 | 3 of 3 |
| Structure034-D6 | 12% | — | Submitted | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-08-22 | V1 | 1 of 3 |
| Finishes034-D7 | 12% | — | Draft | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-10-23 | V0 | 0 of 3 |
| Supply034-D8 | 10% | — | Draft | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-12-24 | V0 | 0 of 3 |
| Installation034-D9 | 10% | — | Draft | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2027-02-25 | V0 | 0 of 3 |
| Testing & commissioning034-D10 | 9% | — | Draft | Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.sy | Eng. Fadi Al-Droubi | 2027-04-28 | V0 | 0 of 3 |
| Provisional acceptance034-D11 | 7% | — | Draft | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2027-06-30 | V0 | 0 of 3 |
| Final acceptance034-D12 | 7% | — | Draft | Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.sy | Eng. Fadi Al-Droubi | 2027-08-31 | V0 | 0 of 3 |
| Total · 12 | 100% |