PRJ-2026-034At risk4ExecutionConstructionIn progressDelivered by:Ministry of Public Works and Housing

Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate

Add to watchlist

Rehabilitating roads, water and drainage networks and street lighting in Maarat al-Numan with Idlib Governorate, so residents and public services can return.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SYP 6B

Actual cost

SYP 2B

⁦34%⁩ of budget

Progress

⁦33%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 6.2B

+SYP 247.9M

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure29 June 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to workSYP5.8B⁦17⁩ elements
Unallocated contingencySYP178.5MSYP 297.5M
Budget at completionSYP6BPRJ-2026-034
Weighted progress⁦33%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSYP MActualSYP MLinksDeliverables
Project813⁦2025-07-06⁩⁦2027-09-27⁩⁦33%⁩5,771.502,045.31—
1
Phase223⁦2025-07-06⁩⁦2026-02-14⁩⁦100%⁩346.29372.48—
1.1
WBS element137⁦2025-07-06⁩⁦2025-11-20⁩⁦100%⁩173.15186.240 / 1
1.2
WBS element137⁦2025-09-30⁩⁦2026-02-14⁩⁦100%⁩173.15186.241 / 2
2
Phase223⁦2025-12-24⁩⁦2026-08-04⁩⁦100%⁩692.58744.95—
2.1
WBS element137⁦2025-12-24⁩⁦2026-05-10⁩⁦100%⁩346.29372.481 / 1
2.2
WBS element137⁦2026-03-20⁩⁦2026-08-04⁩⁦100%⁩346.29372.481 / 2
3
Phase291⁦2026-05-14⁩⁦2027-03-01⁩⁦39%⁩2,193.17927.88—
3.1
WBS element135⁦2026-06-13⁩⁦2026-10-26⁩⁦100%⁩731.06786.341 / 1
3.2
WBS element249⁦2026-05-14⁩⁦2027-01-18⁩⁦18%⁩731.06141.541 / 1
3.3
WBS element67⁦2026-12-24⁩⁦2027-03-01⁩⁦0%⁩731.06—1 / 2
4
Phase151⁦2027-02-04⁩⁦2027-07-05⁩⁦0%⁩1,731.45——
4.1
WBS element67⁦2027-02-04⁩⁦2027-04-12⁩⁦0%⁩577.15—1 / 1
4.2
WBS element67⁦2027-03-18⁩⁦2027-05-24⁩⁦0%⁩577.15—1 / 1
4.3
WBS element67⁦2027-04-29⁩⁦2027-07-05⁩⁦0%⁩577.15—1 / 2
5
Phase109⁦2027-06-10⁩⁦2027-09-27⁩⁦0%⁩808.01——
5.1
WBS element67⁦2027-06-10⁩⁦2027-08-16⁩⁦0%⁩404.01—1 / 1
5.2
WBS element67⁦2027-07-22⁩⁦2027-09-27⁩⁦0%⁩404.01—1 / 1
Total⁦33%⁩5,771.502,045.31