Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-034At risk4ExecutionConstructionIn progressDelivered by:Ministry of Public Works and Housing

Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate

Add to watchlist

Rehabilitating roads, water and drainage networks and street lighting in Maarat al-Numan with Idlib Governorate, so residents and public services can return.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SYP 6B

Actual cost

SYP 2B

⁦34%⁩ of budget

Progress

⁦33%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 6.2B

+SYP 247.9M

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure29 June 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started

Periodic update cards

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Period

October 2026

Draft
Progress
⁦33%⁩
Planned
⁦37%⁩
SPI
0.89
Open the card

Periodic update cards

PeriodStatusProgressCurrent stepDate
October 2026UPD-034-2026-10Draft⁦33%⁩—⁦2026-10-26⁩
September 2026UPD-034-2026-09Approved⁦31%⁩—⁦2026-10-02⁩
August 2026UPD-034-2026-08Approved⁦29%⁩—⁦2026-09-02⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close