PRJ-2026-034At risk4ExecutionConstructionIn progressDelivered by:Ministry of Public Works and Housing

Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate

Add to watchlist

Rehabilitating roads, water and drainage networks and street lighting in Maarat al-Numan with Idlib Governorate, so residents and public services can return.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SYP 6B

Actual cost

SYP 2B

⁦34%⁩ of budget

Progress

⁦33%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 6.2B

+SYP 247.9M

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure29 June 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
PSA-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2025-07-04⁩
ApprovedPRJ-2026-034Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-034
Project
Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate
Portfolio
Reconstruction & Infrastructure Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Eng. Abdulrahman Al-Kilani
Project manager
Eng. Wael Al-Khawlani

1Objective

Background

Rehabilitating roads, water and drainage networks and street lighting in Maarat al-Numan with Idlib Governorate, so residents and public services can return.

Project objectives

  1. Rebuild damaged areas and provide replacement housing
  2. Comparable public-service quality in every governorate

2Scope

In scope

  • Rehabilitating roads, water and drainage networks and street lighting in Maarat al-Numan with Idlib Governorate, so residents and public services can return.
  • Syrian Arab Building Code compliance
  • An approved plan to keep services running for residents during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2025-08-06⁩
Main deliverable — stage 1⁦2026-08-11⁩
Main deliverable — final stage⁦2027-05-13⁩
Final report⁦2027-08-31⁩
MilestoneDate
Charter approved⁦2025-07-04⁩
Contract signed⁦2025-11-09⁩
50% of works complete⁦2026-08-11⁩
Provisional acceptance⁦2027-06-29⁩
Closure⁦2027-08-31⁩

4RolesAuto-filled

SponsorAuto-filled
Eng. Abdulrahman Al-Kilani
Project ownerAuto-filled
Eng. Fadi Al-Droubi
Project managerAuto-filled
Eng. Wael Al-Khawlani
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
National Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change CommitteeApproves scope, cost and schedule changesWeekly
Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSYP 4.3B
Supervision & consultingSYP 832.5M
Internal teamSYP 535M
Contingency reserve (5%)SYP 297.5M
Approved budgetSYP 6B

Funding

The delivering body’s investment-plan allocations

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the unified contracts law (Law 51 of 2004)

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsSubmitted—⁦2025-06-25⁩ 10:00
2PMO complianceMethodology reviewDr. Reem Al-QabbaniPMO — directorApproved—⁦2025-06-28⁩ 12:30
3Project ownerTechnical acceptanceEng. Fadi Al-DroubiProject ownerApproved—⁦2025-07-01⁩ 09:45
4Budget funding confirmedFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-07-02⁩ 11:10
5Sponsor approvalTechnical acceptanceEng. Abdulrahman Al-KilaniProject sponsorApproved—⁦2025-07-04⁩ 11:00

Signatures

PMO compliance

Dr. Reem Al-Qabbani

Approved⁦2025-06-28⁩

Project owner

Eng. Fadi Al-Droubi

Approved⁦2025-07-01⁩

Budget funding confirmed

Rasha Al-Mudarres

Approved⁦2025-07-02⁩

Sponsor approval

Eng. Abdulrahman Al-Kilani

Approved⁦2025-07-04⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Eng. Wael Al-Khawlani on ⁦2025-06-25⁩

  1. Methodology review

    PMO compliance

    Dr. Reem Al-Qabbani · PMO — director

    Approved · ⁦2025-06-28⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Eng. Fadi Al-Droubi · Project owner

    Approved · ⁦2025-07-01⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-07-02⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Eng. Abdulrahman Al-Kilani · Project sponsor

    Approved · ⁦2025-07-04⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-07-04⁩

    Approved version

    • PMO comments addressed

    Eng. Wael Al-Khawlani

  2. V1Returned for edit⁦2025-06-15⁩

    First draft

    • Returned to detail the budget