RSK-0035Douma Wastewater Treatment Plant

Pile lengths exceeding contract quantities

12MediumOpen

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Gaps between contract and site quantities

Preventive controls

  • Re-measure quantities with the supervising consultant
  • Value engineering on the costliest items

2 / 2

Event

Pile lengths exceeding contract quantities

12MediumTrigger

Quantity variance above 5% of contract value

Contingency

Defer non-critical items to a later phase

Impact

Extra variations and contingency drawn down

SYP 210M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
12Medium

Residual

5
4
3
2
1
1
2
3
4
5
3Low

Exposure

SYP 210M

Residual

⁦75⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 5 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Eng. Qasem Al-Hariri

    Currently followed up here
  2. 2

    Programme manager

    Eng. Qasem Al-Hariri

  3. 3

    PMO director

    Dr. Reem Al-Qabbani

  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • Re-measure quantities with the supervising consultant

    Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy
    In progressIn 48 days2026-12-15
  • Value engineering on the costliest items

    Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy
    Not startedIn 48 days2026-12-15

Trigger

Quantity variance above 5% of contract value

Contingency

Defer non-critical items to a later phase

Esc