Douma Wastewater Treatment Plant
Remove from watchlistA wastewater treatment plant in Douma serving the city and nearby towns, financed by the Syrian Development Fund, with the main trunk lines and treated water reused for irrigation.
Budget (BAC)
Actual cost
46% of budget
Progress
Estimate at completion
+SYP 453.9M
SPI · CPI
Forecast finish
64 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure5 March 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started