RSK-0034Douma Wastewater Treatment Plant

Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16

20CriticalEscalatedMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Clay layers and voids under the southern part of the plant site that the initial soil tests missed

Preventive controls

  • Extra soil tests at axes 12 to 16
  • A change request to redesign the foundations
  • Dewatering at axis 14

1 / 3

Event

Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16

20CriticalTrigger

Excavation stopped at any axis for more than 10 days

Contingency

Switch to deeper rotary-bored piles

Impact

Foundations of five axes redesigned, 55 days late, SYP 675M

SYP 675M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
20Critical

Residual

5
4
3
2
1
1
2
3
4
5
8Medium

Exposure

SYP 675M

Residual

⁦60⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 5 days ago

  1. Project manager

    Eng. Qasem Al-Hariri

    Currently followed up here
  2. Programme manager

    Current level

    Eng. Qasem Al-Hariri

    Automatically at 15 days unreviewed · in 10 days
  3. 3

    PMO director

    Dr. Reem Al-Qabbani

    Automatically at 20 days unreviewed · in 15 days
  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦2⁩ of ⁦3⁩ done
  • Extra soil tests at axes 12 to 16

    Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy
    Done2026-10-202026-10-20
  • A change request to redesign the foundations

    Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy
    Done2026-09-282026-09-28
  • Dewatering at axis 14

    Eng. Adnan Al-MohammadEng. Adnan Al-MohammadSenior Site Engineer (Contractor)P-043adnan.almohammad@psa.gov.sy
    In progressIn 11 days2026-11-08

Trigger

Excavation stopped at any axis for more than 10 days

Contingency

Switch to deeper rotary-bored piles

Esc