CR-2026-010Douma Wastewater Treatment Plant

Redesign the treatment-basin foundations on axes 12 to 16

ScopeIn reviewImpact level: Major9 days overdue2026-10-19

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SYP 210M

Current budgetSYP 8.6B

After the changeSYP 8.8B

+2.4%

Schedule

+⁦55⁩ d
  • Baseline finish2027-05-31
  • New finish2027-07-25

Risk

−12

Benefits

0%

No effect on benefits

⁦0⁩% of expected benefits

Reason for change

Unforeseen ground at axes 12 to 16

Justification

The current design misses the required safety factor

PMO recommendation

Approve

The national PMO recommends urgent approval: every day of delay costs SYP 3.75M

Approval workflow

  1. Submitted

    Eng. Qasem Al-Hariri

    Done2026-09-28

  2. PM review

    Eng. Qasem Al-Hariri

    Done2026-09-29

  3. Impact analysis

    Kinan Azzam

    Done2026-10-03

  4. Finance & procurement

    Rasha Al-Mudarres

    Done2026-10-04

  5. Project owner’s acceptance

    Jwan Othman

    Done2026-10-04

  6. 6

    Change committee recommendation

    Dr. Ziad Al-Atassi

    Now2026-10-29

  7. 7

    Executive Council decision

    Dr. Samer Al-Daqqar

    Later

  8. 8

    Baseline updated

    Eng. Qasem Al-Hariri

    Later

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelMajorAbove SYP 125M or 90 days

  • A cost impact of SYP 210M is above SYP 125M — «major»: the Change Committee recommends and the Executive Council decides.
  • It has a financial link, so Finance & Procurement take part before the decision.
  • It changes scope or deliverables, so the project owner must accept it.

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

Change Committee — meeting 4229 October 2026 13:00Meeting room 3 — fifth floor
  • Dr. Ziad Al-AtassiDeputy President, Strategy & PerformanceDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syChairNot voted
  • Dr. Reem Al-QabbaniDirector, National Project Management OfficeDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.syYouApprove
  • Omar Al-NahhasSenior Finance & Contracts SpecialistOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syApprove
  • Rasha Al-MudarresDirector General, Finance & ContractsRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.syApprove
  • Eng. Rita GhanemEnterprise ArchitectEng. Rita GhanemEnterprise ArchitectP-031rita.ghanem@psa.gov.syNot voted
  • Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syApprove
4/6Quorum met
  • Approve4
  • Approve with conditions0
  • Reject0
  • Abstain0

Quorum met · Awaiting the change committee’s decision in meeting ⁦42⁩