PRJ-2026-020Off track4ExecutionConstructionStalledDelivered by:Ministry of Local Administration and Environment

Douma Wastewater Treatment Plant

Remove from watchlist

A wastewater treatment plant in Douma serving the city and nearby towns, financed by the Syrian Development Fund, with the main trunk lines and treated water reused for irrigation.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SYP 8.6B

Actual cost

SYP 4B

⁦46%⁩ of budget

Progress

⁦44%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 9.1B

+SYP 453.9M

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure5 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started

Change request

The change, its impact analysis and the approval decision

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
PSA-PMO-F09
Template edition
3.1
Version
V1
Form date
⁦2026-09-28⁩
In approvalCR-2026-010Redesign the treatment-basin foundations on axes 12 to 16

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-020
Project
Douma Wastewater Treatment Plant
Portfolio
Reconstruction & Infrastructure Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Qasem Al-Hariri

1The change

TitleAuto-filled
Redesign the treatment-basin foundations on axes 12 to 16
KindAuto-filled
Scope
Requested byAuto-filled
Eng. Qasem Al-Hariri
Raised onAuto-filled
⁦2026-09-28⁩

Reason

Unforeseen ground at axes 12 to 16

Justification

The current design misses the required safety factor

2Impact analysis

Cost

+SYP 210M

Schedule

+55 days

Risk

20 → 8

Benefits

0%

Risk impact

Treats the treatment basins’ critical risk

Benefits impact

No effect on benefits

3The approval decision

The PMO’s recommendation

The national PMO recommends urgent approval: every day of delay costs SYP 3.75M

Change Committee decision
Not taken yet
Decided on
—
Decision number
—

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Qasem Al-HaririDirector, Transport & Housing ProjectsSubmitted—⁦2026-09-28⁩ 10:49
2Project managerTechnical acceptanceEng. Qasem Al-HaririProject managerApproved—⁦2026-09-29⁩ 12:03
3PMO review & impact analysisMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-09-30⁩ 13:10
4Financial impactFinancial approvalApproval engineFinancePre-breach alert—⁦2026-10-04⁩ 08:00

Signatures

Project manager

Eng. Qasem Al-Hariri

Approved⁦2026-09-29⁩

PMO review & impact analysis

Mariam Al-Zoubi

Approved⁦2026-09-30⁩

Financial impact

Rasha Al-Mudarres

Awaiting decision

Contractual impact

Abdullah Al-Ujaili

Later

Change Committee

Dr. Ziad Al-Atassi

Later

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F09 · version V1

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Eng. Qasem Al-Hariri on ⁦2026-09-28⁩

  1. Technical acceptance

    Project manager

    Eng. Qasem Al-Hariri · Project manager

    Approved · ⁦2026-09-29⁩ at ⁦12:03⁩

  2. Methodology review

    PMO review & impact analysis

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-09-30⁩ at ⁦13:10⁩

  3. Financial approval

    Financial impact

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Delegated to Omar Al-Nahhas

    18 working days overdueAction time limit exceeded · Limit 2 working daysLimit 2 working days · Due ⁦2026-10-04⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-10-04⁩

    Waiting on Omar Al-Nahhas
  4. Financial approval

    Contractual impact

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Limit 2 working days · Expected by ⁦2026-10-06⁩

  5. Technical acceptance

    Change Committee

    Dr. Ziad Al-Atassi · Change Committee

    Delegated to Dr. Reem Al-Qabbani

    Limit 3 working days · Expected by ⁦2026-10-11⁩

Steps that do not apply to this record

  • National Projects Steering Committee — the condition «Cost impact above the Change Committee’s authority?» does not holdFrom the authority matrix
  • Authority Executive Council — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-09-28⁩

    The request as raised

    Eng. Qasem Al-Hariri

Only one version so far.