PRJ-2026-020Off track4ExecutionConstructionStalledDelivered by:Ministry of Local Administration and Environment
Douma Wastewater Treatment Plant
Remove from watchlist
A wastewater treatment plant in Douma serving the city and nearby towns, financed by the Syrian Development Fund, with the main trunk lines and treated water reused for irrigation.
Early warning: 81% chance of slipping within 60 days
Budget (BAC)
SYP 8.6B
Actual cost
SYP 4B
46% of budget
Progress
44%Awaiting acceptance 12%
Estimate at completion
SYP 9.1B
+SYP 453.9M
SPI · CPI
0.80Schedule performance index · 0.800.95Cost performance index · 0.95
Forecast finish
2027-08-03
64 days behind baseline
Execution·Stage 4 of 5
Next gate:Closure5 March 2027
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.