Original
Original baseline
- Finish
- 2027-05-31
- Budget
- SYP 8.6B
- 17 activities
Approved with the project plan at the planning gate.
Approved 2024-06-02 · by Salma Al-Zaim
A wastewater treatment plant in Douma serving the city and nearby towns, financed by the Syrian Development Fund, with the main trunk lines and treated water reused for irrigation.
Budget (BAC)
Actual cost
46% of budget
Progress
Estimate at completion
+SYP 453.9M
SPI · CPI
Forecast finish
64 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure5 March 2027
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2024-06-02 · by Salma Al-Zaim
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Qasem Al-Hariri
What changed from version A to version B
Finish
2027-05-312027-08-01
+62 days
Budget
SYP 8.6BSYP 8.8B
+210.00 SYP M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SYP millions from A to B
Every saved version with its reason and reference