AI insight
58% chance of a further slip within 45 days
From the SPI trend (0.88), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
Solar lighting for the highway between As-Sanamayn and Daraa: 1,200 lighting poles and traffic cameras, smart signals at the junctions and a traffic control room in Daraa.
Budget (BAC)
Actual cost
84% of budget
Progress
Estimate at completion
+SYP 118.1M
SPI · CPI
Forecast finish
45 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure11 September 2026
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
76
Needs watching
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
From the SPI trend (0.88), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
Generated from the live project data
The project is behind plan: 79% done against 90% planned.
SPI 0.88, CPI 0.94.
How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.
The main objective and initiative, the secondary links, and the project’s contribution to its initiative.
Main initiative
SI-2.1.1National connectivity & support services
The project’s share of the initiative’s project budget (4 projects)
Secondary links
Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.
Counted
79%Awaiting acceptance 9%
Not handed in 12%
9 deliverables accepted
1 deliverable under inspection or acceptance
Corrective plan requiredThe project is seriously late (45 days late) and has no corrective plan yet.
4 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 93% of budget
1 approval and 1 open action on this project
From «My actions» for this project
1 open
Cost and schedule impact
2 open risks, exposure SYP 80M
Impact
9 of 12 approved
2 members