PRJ-2026-013At risk4ExecutionConstructionIn progressDelivered by:Ministry of Transport

Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals

Add to watchlist

Solar lighting for the highway between As-Sanamayn and Daraa: 1,200 lighting poles and traffic cameras, smart signals at the junctions and a traffic control room in Daraa.

Early warning: ⁦58%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 1.9B

Actual cost

SYP 1.6B

⁦84%⁩ of budget

Progress

⁦79%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 2B

+SYP 118.1M

SPI · CPI

0.88Schedule performance index · 0.880.94Cost performance index · 0.94

Forecast finish

⁦2026-12-15⁩

45 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure11 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−6

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦58%⁩ chance of a further slip within ⁦45⁩ days

From the SPI trend (⁦0.88⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦79% done against 90% planned⁩.

⁦SPI 0⁩.⁦88⁩, ⁦CPI 0⁩.⁦94⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Reconstruction & InfrastructureSO-2.1Rehabilitate core energy, water and transport infrastructure

Main initiative

SI-2.1.1National connectivity & support services

Contribution to the initiative⁦20%⁩

The project’s share of the initiative’s project budget (4 projects)

Secondary links

Annual work-plan line
Added outside the annual work plan
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦79%⁩

Awaiting acceptance ⁦9%⁩

Not handed in ⁦12%⁩

9 deliverables accepted

  • Site works & excavation⁦13%⁩
  • Structure⁦13%⁩
  • Finishes⁦13%⁩
  • Supply⁦11%⁩
  • Installation⁦11%⁩
  • Detailed design⁦6%⁩
  • Permits & approvals⁦6%⁩
  • Project plan & baseline⁦3%⁩

1 deliverable under inspection or acceptance

  • Testing & commissioning⁦9%⁩

Corrective plan requiredThe project is seriously late (45 days late) and has no corrective plan yet.

Progress & earned value

⁦4⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦93%⁩ of budget

SYP1.6B/ SYP1.9BSYP118.1Mprojected overrun(⁦6.4%⁩)
Actual spend
SYP1.6B
Committed
SYP1.7B
Approved budget
SYP1.9B
Estimate at completion
SYP2B

Next milestones

  • Closure⁦2026-12-15⁩was ⁦2026-10-31⁩Late

Waiting on someone

⁦1⁩ approval and ⁦1⁩ open action on this project

Approvals & requests

From «My actions» for this project

Actions

⁦1⁩ open

  • Update progress and the plan in MunjazEng. Maher Al-Hamawi7 days overdue2026-10-21Medium

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

2 open risks, exposure SYP 80M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0030Quantity gaps in lighting poles and cameras between drawings and site1Probability: Possible · Impact: MajorMedium · Score ⁦12⁩RSK-0031Late link-up of the Daraa traffic control room with the smart signalsProbability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium2
  • Low0

Deliverables

⁦9⁩ of ⁦12⁩ approved

  • Project plan & baseline013-D1 · V1 · CRT-013-01⁦3%⁩Eng. Maher Al-Hamawi2025-05-062025-05-06Approved
  • Monitoring & reporting013-D2 · V1 · CRT-013-02⁦3%⁩Eng. Wassim Al-Azm2025-06-242025-06-24Approved
  • Detailed design013-D3 · V1 · CRT-013-03⁦6%⁩Eng. Wassim Al-Azm2025-08-132025-08-13Approved
  • Permits & approvals013-D4 · V1 · CRT-013-04⁦6%⁩Salma Al-Zaim2025-10-012025-10-01Approved
  • Site works & excavation013-D5 · V1 · CRT-013-05⁦13%⁩Salma Al-Zaim2025-11-192025-11-19Approved
  • Structure013-D6 · V1 · CRT-013-06⁦13%⁩Eng. Maher Al-Hamawi2026-01-082026-01-08Approved
  • Finishes013-D7 · V1 · CRT-013-07⁦13%⁩Eng. Wassim Al-Azm2026-02-262026-02-26Approved
  • Supply013-D8 · V1 · CRT-013-08⁦11%⁩Eng. Maher Al-Hamawi2026-04-172026-04-17Approved
  • Installation013-D9 · V1 · CRT-013-09⁦11%⁩Eng. Wassim Al-Azm2026-06-052026-06-05Approved
  • Testing & commissioning013-D10 · V1⁦9%⁩Salma Al-Zaim96 days overdue2026-07-24Submitted
  • Provisional acceptance013-D11 · V0⁦6%⁩Eng. Wassim Al-Azm46 days overdue2026-09-12Draft
  • Final acceptance013-D12 · V0⁦6%⁩Salma Al-ZaimIn 3 days2026-10-31Draft

Team, contracts & documents

Team

2 members

Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities ProjectsEng. Wassim Al-Azm · Director General, Infrastructure & Reconstruction Projects
  • Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsProject managerP-021maher.alhamawi@psa.gov.sy⁦30%⁩
  • Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsProject ownerP-013wassim.alazm@psa.gov.sy⁦15%⁩