PRJ-2026-013At risk4ExecutionConstructionIn progressDelivered by:Ministry of Transport

Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals

Add to watchlist

Solar lighting for the highway between As-Sanamayn and Daraa: 1,200 lighting poles and traffic cameras, smart signals at the junctions and a traffic control room in Daraa.

Early warning: ⁦58%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 1.9B

Actual cost

SYP 1.6B

⁦84%⁩ of budget

Progress

⁦79%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 2B

+SYP 118.1M

SPI · CPI

0.88Schedule performance index · 0.880.94Cost performance index · 0.94

Forecast finish

⁦2026-12-15⁩

45 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure11 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2026-10-31⁩
    Budget
    SYP 1.9B
    ⁦17⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2025-02-16⁩ · by Salma Al-Zaim

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-01-11⁩
    ⁦+72⁩ days
    Budget
    SYP 1.9B
    ⁦17⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Eng. Maher Al-Hamawi

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2026-10-31⁩⁦2027-01-11⁩

⁦+72⁩ days

Budget

SYP 1.9BSYP 1.9B

⁦0.00⁩ SYP M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2025-072026-012026-072027-01
  • Project plan approved⁦+40⁩
  • Designs approved⁦+70⁩
  • Build complete⁦+115⁩
  • Testing & acceptance complete⁦+151⁩
  • Final handover⁦+72⁩

Version AVersion B

Cost by WBS element

Difference in SYP millions from A to B

  • 1Management & governance⁦+10.42⁩
  • 2Design & permits⁦+20.83⁩
  • 3Civil works⁦+102.96⁩
  • 4MEP works⁦+12.37⁩
  • 5Handover⁦+36.26⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Eng. Maher Al-Hamawi
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2025-02-16⁩by Salma Al-Zaim