Original
Original baseline
- Finish
- 2026-10-31
- Budget
- SYP 1.9B
- 17 activities
Approved with the project plan at the planning gate.
Approved 2025-02-16 · by Salma Al-Zaim
Solar lighting for the highway between As-Sanamayn and Daraa: 1,200 lighting poles and traffic cameras, smart signals at the junctions and a traffic control room in Daraa.
Budget (BAC)
Actual cost
84% of budget
Progress
Estimate at completion
+SYP 118.1M
SPI · CPI
Forecast finish
45 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure11 September 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-02-16 · by Salma Al-Zaim
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Maher Al-Hamawi
What changed from version A to version B
Finish
2026-10-312027-01-11
+72 days
Budget
SYP 1.9BSYP 1.9B
0.00 SYP M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SYP millions from A to B
Every saved version with its reason and reference