Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-013At risk4ExecutionConstructionIn progressDelivered by:Ministry of Transport

Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals

Add to watchlist

Solar lighting for the highway between As-Sanamayn and Daraa: 1,200 lighting poles and traffic cameras, smart signals at the junctions and a traffic control room in Daraa.

Early warning: ⁦58%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 1.9B

Actual cost

SYP 1.6B

⁦84%⁩ of budget

Progress

⁦79%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 2B

+SYP 118.1M

SPI · CPI

0.88Schedule performance index · 0.880.94Cost performance index · 0.94

Forecast finish

⁦2026-12-15⁩

45 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure11 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started

Periodic update cards

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Period

October 2026

Draft
Progress
⁦79%⁩
Planned
⁦90%⁩
SPI
0.88
Open the card

Periodic update cards

PeriodStatusProgressCurrent stepDate
October 2026UPD-013-2026-10Draft⁦79%⁩—⁦2026-10-26⁩
September 2026UPD-013-2026-09Approved⁦75%⁩—⁦2026-10-02⁩
August 2026UPD-013-2026-08Approved⁦70%⁩—⁦2026-09-02⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close