Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals
Add to watchlistSolar lighting for the highway between As-Sanamayn and Daraa: 1,200 lighting poles and traffic cameras, smart signals at the junctions and a traffic control room in Daraa.
Budget (BAC)
Actual cost
84% of budget
Progress
Estimate at completion
+SYP 118.1M
SPI · CPI
Forecast finish
45 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure11 September 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started