PRJ-2026-013At risk4ExecutionConstructionIn progressDelivered by:Ministry of Transport

Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals

Add to watchlist

Solar lighting for the highway between As-Sanamayn and Daraa: 1,200 lighting poles and traffic cameras, smart signals at the junctions and a traffic control room in Daraa.

Early warning: ⁦58%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 1.9B

Actual cost

SYP 1.6B

⁦84%⁩ of budget

Progress

⁦79%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 2B

+SYP 118.1M

SPI · CPI

0.88Schedule performance index · 0.880.94Cost performance index · 0.94

Forecast finish

⁦2026-12-15⁩

45 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure11 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Planning and Statistics Authority

Project charter

Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals

APPROVEDV2Approved ⁦2025-02-14⁩

1Project identity

Required at this stage
Project name
Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals
Project code
PRJ-2026-013
Project sponsor
Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy
Project manager
Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy
Project owner
Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy
Portfolio & programme
Reconstruction & Infrastructure PortfolioNational Connectivity & Support Services Programme
Type & methodology
Infrastructure · Construction
Current phase
4Execution

2Background & rationale

Required at this stage

Solar lighting for the highway between As-Sanamayn and Daraa: ⁦1,200 lighting poles and traffic cameras⁩, smart signals at the junctions and a traffic control room in Daraa.

3Objectives

Required at this stage
  1. 1Rehabilitate core energy, water and transport infrastructure
  2. 2Governorate plans and a balanced share of public investment

4Scope

Required at this stage

In scope

  • Solar lighting for the highway between As-Sanamayn and Daraa: ⁦1,200 lighting poles and traffic cameras⁩, smart signals at the junctions and a traffic control room in Daraa.
  • Syrian Arab Building Code compliance
  • An approved plan to keep services running for residents during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Syrian Arab Building Code compliance
  2. 2An approved plan to keep services running for residents during the works
  3. 3Civil-defence requirements

6Deliverables

Required at this stage
1Project management plan⁦2025-03-13⁩
2Main deliverable — stage 1⁦2025-12-31⁩
3Main deliverable — final stage⁦2026-08-05⁩
4Final report⁦2026-10-31⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2025-02-14⁩
  2. Contract signed⁦2025-05-27⁩
  3. 50% of works complete⁦2025-12-31⁩
  4. Provisional acceptance⁦2026-09-11⁩
  5. Closure⁦2026-10-31⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩SYP1.3B
  • Supervision & consulting⁦13.9%⁩SYP257.5M
  • Internal team⁦9.1%⁩SYP167.5M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩SYP92.5M
The delivering body’s investment-plan allocationsTotalSYP1.9B

9Timeline

Required at this stage
Start
2025-02-1616 February 2025
Baseline finish
2026-10-3131 October 2026
Duration
⁦20⁩ months

10Key risks

Required at this stage
  • MediumQuantity gaps in lighting poles and cameras between drawings and site
  • MediumLate link-up of the Daraa traffic control room with the smart signals

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the unified contracts law (⁦Law 51 of 2004⁩)

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • National Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Authority