PRJ-2026-013At risk4ExecutionConstructionIn progressDelivered by:Ministry of Transport

Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals

Add to watchlist

Solar lighting for the highway between As-Sanamayn and Daraa: 1,200 lighting poles and traffic cameras, smart signals at the junctions and a traffic control room in Daraa.

Early warning: ⁦58%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 1.9B

Actual cost

SYP 1.6B

⁦84%⁩ of budget

Progress

⁦79%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 2B

+SYP 118.1M

SPI · CPI

0.88Schedule performance index · 0.880.94Cost performance index · 0.94

Forecast finish

⁦2026-12-15⁩

45 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure11 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
PSA-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2025-03-13⁩
ApprovedPRJ-2026-013Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-013
Project
Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals
Portfolio
Reconstruction & Infrastructure Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Maher Al-Hamawi

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2025-02-16⁩

Baseline finish

⁦2026-10-31⁩

Forecast finish

⁦2026-12-15⁩

SPI

0.88

MilestonePlannedForecastSlip
Project plan approved⁦2025-06-24⁩⁦2025-08-03⁩+40 days
Designs approved⁦2025-10-01⁩⁦2025-12-10⁩+70 days
Build complete⁦2026-02-26⁩⁦2026-06-21⁩+115 days
Testing & acceptance complete⁦2026-07-24⁩⁦2026-12-22⁩+151 days
Final handover⁦2026-10-31⁩⁦2027-01-11⁩+72 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦3%⁩⁦2025-05-06⁩Eng. Maher Al-Hamawi
Monitoring & reporting⁦3%⁩⁦2025-06-24⁩Eng. Wassim Al-Azm
Detailed design⁦6%⁩⁦2025-08-13⁩Eng. Wassim Al-Azm
Permits & approvals⁦6%⁩⁦2025-10-01⁩Salma Al-Zaim
Site works & excavation⁦13%⁩⁦2025-11-19⁩Salma Al-Zaim
Structure⁦13%⁩⁦2026-01-08⁩Eng. Maher Al-Hamawi
Finishes⁦13%⁩⁦2026-02-26⁩Eng. Wassim Al-Azm
Supply⁦11%⁩⁦2026-04-17⁩Eng. Maher Al-Hamawi
Installation⁦11%⁩⁦2026-06-05⁩Eng. Wassim Al-Azm
Testing & commissioning⁦9%⁩⁦2026-07-24⁩Salma Al-Zaim
Provisional acceptance⁦6%⁩⁦2026-09-12⁩Eng. Wassim Al-Azm
Final acceptance⁦6%⁩⁦2026-10-31⁩Salma Al-Zaim
Accepted with a certificate⁦79%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0031Late link-up of the Daraa traffic control room with the smart signals12MitigateEng. Maher Al-Hamawi
RSK-0030Quantity gaps in lighting poles and cameras between drawings and site9MitigateEng. Maher Al-Hamawi

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyEng. Maher Al-Hamawi
Project ownerDeliverable status and acceptance datesFortnightlyEng. Maher Al-Hamawi
PMOData and indicator updatesWeeklyEng. Maher Al-Hamawi
BeneficiariesWhat changes and whenAt each milestoneEng. Maher Al-Hamawi
Team memberRoleAllocation
Eng. Maher Al-HamawiProject manager⁦30%⁩
Eng. Wassim Al-AzmProject owner⁦15%⁩

5QualityAuto-filled

Quality leadAuto-filled
Eng. Maher Al-Hamawi
Review cadenceAuto-filled
Sample checks on every delivery batch
Next reviewAuto-filled
⁦2026-10-31⁩
Quality criterionThresholdNowMet
Camera and smart-signal conformity certificatesA standards conformity certificate per batchMissing for 2 of 7 batchesNo
Cameras and signals on the central control room100% at handover67%No

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsSubmitted—⁦2025-03-13⁩ 14:47
2Methodology review — PMOMethodology reviewMariam Al-ZoubiPMO — analystApprovedComplete against the project management plan template.⁦2025-03-17⁩ 10:49
3Technical acceptance — project ownerTechnical acceptanceEng. Wassim Al-AzmProject ownerApproved—⁦2025-03-20⁩ 11:56
4Cash flow & financial commitmentFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-03-23⁩ 09:42
5Plan aligned with the contractsFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2025-03-25⁩ 10:19
6Sponsor approvalTechnical acceptanceSalma Al-ZaimProject sponsorApproved—⁦2025-03-30⁩ 14:17

Signatures

Methodology review — PMO

Mariam Al-Zoubi

Approved⁦2025-03-17⁩

Technical acceptance — project owner

Eng. Wassim Al-Azm

Approved⁦2025-03-20⁩

Cash flow & financial commitment

Rasha Al-Mudarres

Approved⁦2025-03-23⁩

Plan aligned with the contracts

Abdullah Al-Ujaili

Approved⁦2025-03-25⁩

Sponsor approval

Salma Al-Zaim

Approved⁦2025-03-30⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Maher Al-Hamawi on ⁦2025-03-13⁩

  1. Methodology review

    Methodology review — PMO

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-03-17⁩ at ⁦10:49⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Eng. Wassim Al-Azm · Project owner

    Approved · ⁦2025-03-20⁩ at ⁦11:56⁩

  3. Financial approval

    Cash flow & financial commitment

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-03-23⁩ at ⁦09:42⁩

  4. Financial approval

    Plan aligned with the contracts

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-03-25⁩ at ⁦10:19⁩

  5. Technical acceptance

    Sponsor approval

    Salma Al-Zaim · Project sponsor

    Approved · ⁦2025-03-30⁩ at ⁦14:17⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-03-13⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Maher Al-Hamawi

  2. V1Returned for edit⁦2025-02-27⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Eng. Maher Al-Hamawi