RSK-0030Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals

Quantity gaps in lighting poles and cameras between drawings and site

9MediumOpen

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Price swings and unplanned financial commitments

Preventive controls

  • Monthly EAC monitoring
  • Fix prices in the coming purchase orders

2 / 2

Event

Quantity gaps in lighting poles and cameras between drawings and site

9MediumTrigger

EAC above budget by more than 5%

Contingency

Reallocate from the portfolio reserve

Impact

Budget overrun and the need for more funding

SYP 45M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
9Medium

Residual

5
4
3
2
1
1
2
3
4
5
2Low

Exposure

SYP 45M

Residual

⁦78⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 44 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Eng. Maher Al-Hamawi

    Currently followed up here
  2. 2

    Programme manager

    Eng. George Haddad

  3. 3

    PMO director

    Dr. Reem Al-Qabbani

  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • Monthly EAC monitoring

    Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy
    In progressIn 33 days2026-11-30
  • Fix prices in the coming purchase orders

    Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy
    Not startedIn 33 days2026-11-30

Trigger

EAC above budget by more than 5%

Contingency

Reallocate from the portfolio reserve

Esc