PSA/2025/002
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
82% of the current value paid
Paid
SYP1.3Bof a current value of SYP 1.5B
Supply and install 1,200 lighting poles, cameras and smart signals on the Damascus–Daraa highway with a central control room, traffic management and automatic incident alerts, plus two years of maintenance.
Monthly certificates on quantities measured and certified by the consultant, paid within 30 days of approval; the advance is recovered from each certificate.
Payment period
30 days
Retention
10%
Released at final acceptance
Advance payment
10%
Recovered from certificates
Penalty cap
10%
Of the contract value
Defects liability
12 months
After substantial completion
Bar: paid share of the value; gold mark: today
Met: 3 of 4
| Measure | Target | Achieved | Breach penalty |
|---|---|---|---|
| HSE incident notification | within 24 h | 2 reported after 48 h | SYP1.3M |
| Non-conformance close-out | within 14 days | average 9 days | — |
| Monthly progress report | by the 5th of the month | on time | — |
| Actual vs planned manpower | at least 90% | 94% | — |
Integration-ready for the ERP contracts & procurement moduleIntegration-ready
Tender file no. — General Authority for Supply and Provision: 2503250420
The integration layer is in place; data exchange starts once the permissions and interfaces are granted.
Bank guarantees and insurance policies with their expiry