Certificate ⁦4⁩ — July 2025

Supply & install lighting, cameras, smart signals and the control room — southern M5

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
4
Date
⁦2025-08-06⁩
Reference
PAY-2025-002-04

Interim payment certificate no. (⁦4⁩)

For the work of July 2025

Contract number
PSA/2025/002
Tender file no.
2503250420
Contract
Supply & install lighting, cameras, smart signals and the control room — southern M5
Contractor
Modern Networks Telecom Co.
Contractor tax number
TX-409411
Project
Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals
Contract period
⁦2025-03-02⁩ — ⁦2026-10-31⁩
Original contract value
SYP1,537,500,000
Current contract value
SYP1,537,500,000
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SYP)

1Total value of work completed to date293,250,000
2Less: previous certificates(187,000,000)
3Value of work in this certificate106,250,000
4Less: retention (⁦10%⁩)(10,625,000)
5Less: advance payment recovery (⁦10%⁩)(10,625,000)
6Less: delay and breach penalties0
7Total deductions(21,250,000)
8Net amount payable to the contractorSYP85,000,000

Amount in words: Eighty-five million Syrian pounds only

Retention held up to this certificate: SYP 29.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation107,625,00031,100,00016,250,00047,350,000⁦44%⁩
Earthworks & foundations276,750,00048,150,00025,750,00073,900,000⁦27%⁩
Concrete & structural works476,625,00063,675,00036,325,000100,000,000⁦21%⁩
Mechanical, electrical & plumbing369,000,00030,400,00018,875,00049,275,000⁦13%⁩
Finishes & external works230,625,00011,975,0007,825,00019,800,000⁦9%⁩
Testing & commissioning76,875,0001,700,0001,225,0002,925,000⁦4%⁩
Total1,537,500,000187,000,000106,250,000293,250,000⁦19%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ammar Al-Ahmad

Al-Ahmad⁦2025-08-06⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-08-08⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2025-08-11⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2025-08-14⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2025-08-17⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-08-06⁩

    Eng. Ammar Al-Ahmad

  2. Engineer verifies quantities⁦2025-08-08⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-08-11⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2025-08-14⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-08-17⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2025-08-19⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2025-12-10⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Dr. Samer Al-Daqqar

Certificate history

17 August 2025

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2025-08-17 13:00

14 August 2025

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2025-08-14 13:00

11 August 2025

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2025-08-11 13:00

8 August 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2025-08-08 13:00

6 August 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-08-06 09:00