PSA/2025/002
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
82% of the current value paid
Paid
SYP1.3Bof a current value of SYP 1.5B
Value of each certificate
The last 14 — gross and net
Approved: 14
Count: 14 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | Net | Status | |
|---|---|---|---|---|---|---|---|
| Certificate 14July 2026 | 2026-08-09 | SYP82.5M | SYP8.3M | SYP8.3M | SYP66M | Approved | |
| Certificate 13June 2026 | 2026-07-08 | SYP43.5M | SYP4.4M | SYP4.4M | SYP34.8M | Approved | |
| Certificate 12May 2026 | 2026-06-01 | SYP65M | SYP6.5M | SYP6.5M | SYP52M | Approved | |
| Certificate 11April 2026 | 2026-04-24 | SYP77.3M | SYP7.7M | SYP7.7M | SYP61.8M | Approved | |
| Certificate 10February 2026 | 2026-03-18 | SYP110M | SYP11M | SYP11M | SYP88M | Approved | |
| Certificate 9January 2026 | 2026-02-09 | SYP107.5M | SYP10.8M | SYP10.8M | SYP86M | Approved | |
| Certificate 8December 2025 | 2026-01-02 | SYP115.5M | SYP11.6M | SYP11.6M | SYP92.4M | Approved | |
| Certificate 7November 2025 | 2025-11-26 | SYP136M | SYP13.6M | SYP13.6M | SYP108.8M | Approved | |
| Certificate 6September 2025 | 2025-10-20 | SYP109M | SYP10.9M | SYP10.9M | SYP87.2M | Approved | |
| Certificate 5August 2025 | 2025-09-12 | SYP115.5M | SYP11.6M | SYP11.6M | SYP92.4M | Approved | |
| Certificate 4July 2025 | 2025-08-06 | SYP106.3M | SYP10.6M | SYP10.6M | SYP85M | Approved | |
| Certificate 3June 2025 | 2025-06-30 | SYP76M | SYP7.6M | SYP7.6M | SYP60.8M | Approved | |
| Certificate 2May 2025 | 2025-05-23 | SYP68M | SYP6.8M | SYP6.8M | SYP54.4M | Approved | |
| Certificate 1March 2025 | 2025-04-16 | SYP43M | SYP4.3M | SYP4.3M | SYP34.4M | Approved |