Certificate ⁦6⁩ — September 2025

Supply & install lighting, cameras, smart signals and the control room — southern M5

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
6
Date
⁦2025-10-20⁩
Reference
PAY-2025-002-06

Interim payment certificate no. (⁦6⁩)

For the work of September 2025

Contract number
PSA/2025/002
Tender file no.
2503250420
Contract
Supply & install lighting, cameras, smart signals and the control room — southern M5
Contractor
Modern Networks Telecom Co.
Contractor tax number
TX-409411
Project
Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals
Contract period
⁦2025-03-02⁩ — ⁦2026-10-31⁩
Original contract value
SYP1,537,500,000
Current contract value
SYP1,537,500,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date517,750,000
2Less: previous certificates(408,750,000)
3Value of work in this certificate109,000,000
4Less: retention (⁦10%⁩)(10,900,000)
5Less: advance payment recovery (⁦10%⁩)(10,900,000)
6Less: delay and breach penalties0
7Total deductions(21,800,000)
8Net amount payable to the contractorSYP87,200,000

Amount in words: Eighty-seven million two hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 51.8M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation107,625,00067,850,00015,775,00083,625,000⁦78%⁩
Earthworks & foundations276,750,000105,125,00025,350,000130,475,000⁦47%⁩
Concrete & structural works476,625,000139,175,00037,375,000176,550,000⁦37%⁩
Mechanical, electrical & plumbing369,000,00066,550,00020,425,00086,975,000⁦24%⁩
Finishes & external works230,625,00026,225,0008,725,00034,950,000⁦15%⁩
Testing & commissioning76,875,0003,825,0001,350,0005,175,000⁦7%⁩
Total1,537,500,000408,750,000109,000,000517,750,000⁦34%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ammar Al-Ahmad

Al-Ahmad⁦2025-10-20⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-10-22⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2025-10-25⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2025-10-28⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2025-10-31⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-10-20⁩

    Eng. Ammar Al-Ahmad

  2. Engineer verifies quantities⁦2025-10-22⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-10-25⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2025-10-28⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-10-31⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeDone · ⁦2026-01-30⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-06-21⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Dr. Samer Al-Daqqar

Certificate history

31 October 2025

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2025-10-31 13:00

28 October 2025

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2025-10-28 13:00

25 October 2025

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2025-10-25 13:00

22 October 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2025-10-22 13:00

20 October 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-10-20 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close