Certificate ⁦10⁩ — February 2026

Supply & install lighting, cameras, smart signals and the control room — southern M5

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
10
Date
⁦2026-03-18⁩
Reference
PAY-2025-002-10

Interim payment certificate no. (⁦10⁩)

For the work of February 2026

Contract number
PSA/2025/002
Tender file no.
2503250420
Contract
Supply & install lighting, cameras, smart signals and the control room — southern M5
Contractor
Modern Networks Telecom Co.
Contractor tax number
TX-409411
Project
Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals
Contract period
⁦2025-03-02⁩ — ⁦2026-10-31⁩
Original contract value
SYP1,537,500,000
Current contract value
SYP1,537,500,000
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SYP)

1Total value of work completed to date986,750,000
2Less: previous certificates(876,750,000)
3Value of work in this certificate110,000,000
4Less: retention (⁦10%⁩)(11,000,000)
5Less: advance payment recovery (⁦10%⁩)(11,000,000)
6Less: delay and breach penalties0
7Total deductions(22,000,000)
8Net amount payable to the contractorSYP88,000,000

Amount in words: Eighty-eight million Syrian pounds only

Retention held up to this certificate: SYP 98.7M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation107,625,00099,025,0008,600,000107,625,000⁦100%⁩
Earthworks & foundations276,750,000252,400,00024,350,000276,750,000⁦100%⁩
Concrete & structural works476,625,000319,750,00040,375,000360,125,000⁦76%⁩
Mechanical, electrical & plumbing369,000,000141,850,00023,925,000165,775,000⁦45%⁩
Finishes & external works230,625,00055,650,00010,950,00066,600,000⁦29%⁩
Testing & commissioning76,875,0008,075,0001,800,0009,875,000⁦13%⁩
Total1,537,500,000876,750,000110,000,000986,750,000⁦64%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Ammar Al-Ahmad

Al-Ahmad⁦2026-03-18⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-03-20⁩

Project manager

Eng. Maher Al-Hamawi

Al-Hamawi⁦2026-03-23⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-03-26⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-03-29⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-03-18⁩

    Eng. Ammar Al-Ahmad

  2. Engineer verifies quantities⁦2026-03-20⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-03-23⁩

    Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities Projects

    Took 3 days

  4. Payment order prepared⁦2026-03-26⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-03-29⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedDone · ⁦2026-06-19⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Maher Al-Hamawi → Dr. Samer Al-Daqqar

Certificate history

29 March 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-03-29 13:00

26 March 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-03-26 13:00

23 March 2026

  1. Approval: Eng. Maher Al-Hamawi signed “Project manager certifies”

    2026-03-23 13:00

20 March 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-03-20 13:00

18 March 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-03-18 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close