Contracts
The contract register with values, variation orders and payments.
- Live contracts
- 31
- Current value
- SYP 91.4B
- Paid to date
- SYP 48.8B
- Retention held
- SYP 4.7B
- Ending within 90 days
- 13
of 33 in the register
Original SYP 88.9B before variations
53% of the current value
Released after final acceptance
Guarantees or policies expiring: 7
Expiry horizon
The year ahead on one line: contract end dates, bank guarantee and insurance expiries — so nothing lapses without a decision.
What ends in the next 12 months
Ending within 90 days: 26 — click any point to open the contract
Contract end · Oct 2026
Contract end · Nov 2026
Contract end · Dec 2026
Contract end · Jan 2027
Contract end · Feb 2027
Contract end · Mar 2027
Contract end · Apr 2027
Contract end · May 2027
Contract end · Jun 2027
Contract end · Aug 2027
Contract end · Sep 2027
Guarantees · Oct 2026
Guarantees · Nov 2026
Guarantees · Dec 2026
Guarantees · Jan 2027
Guarantees · Mar 2027
Guarantees · Apr 2027
Guarantees · May 2027
Guarantees · Jun 2027
Guarantees · Jul 2027
Guarantees · Aug 2027
Guarantees · Sep 2027
Insurance · Oct 2026
Insurance · Dec 2026
Insurance · Jan 2027
Insurance · Feb 2027
Insurance · Mar 2027
Insurance · May 2027
Insurance · Jun 2027
Insurance · Jul 2027
Insurance · Aug 2027
Insurance · Sep 2027
Value by contract type
Live contracts
SYP 91.4B
Current value
- Lump sumSYP 34.6B38%
- RemeasuredSYP 53.1B58%
- Time & materialsSYP 2.4B3%
- Framework agreementSYP 950M1%
- Service contractSYP 352.5M0%
Contract register
Each contract with its original and current value, paid and retained, its dates, securities and performance.
Display options
| Actions | |||||||||
|---|---|---|---|---|---|---|---|---|---|
| PSA/2024/011Darayya replacement housing — construction | Al-Bunyan Al-Mateen Contracting Co. | SYP26.5B+3.8%Original SYP 25.5B, approved variations SYP 962.5M | 41%SYP11B | SYP1.1B10% | 2027-06-30Expires in 245 days | Guarantee2027-07-30Expires in 275 days | 61 | In progress | |
| PSA/2024/006Hama National Hospital extension — civil & MEP works | Al-Fayhaa General Contracting Co. | SYP14.6B+4.3%Original SYP 14B, approved variations SYP 600M | 64%SYP9.3B | SYP928.8M10% | 2026-12-31Expires in 64 days | Guarantee2027-01-30Expires in 94 days | 52 | Escalated | |
| PSA/2024/003Aleppo 230 kV substations — supply, installation & civil works | Al-Shahbaa Construction & Rehabilitation Co. | SYP9.3B+6.1%Original SYP 8.8B, approved variations SYP 535M | 72%SYP6.7B | SYP672.3M10% | 2026-09-30Expired 28 days ago | Guarantee2026-10-30Expires in 2 days | 48 | Escalated | |
| PSA/2024/017Douma wastewater treatment plant — construction | Al-Bunyan Al-Mateen Contracting Co. | SYP7.5BNo variations | 43%SYP3.2B | SYP320.3M10% | 2027-05-31Expires in 215 days | Guarantee2027-06-30Expires in 245 days | 66 | In progress | |
| PSA/2024/019Sheikh Najjar industrial city — civil & ground-improvement works | Al-Sahel Contracting & Development Co. | SYP5.9B+4.2%Original SYP 5.7B, approved variations SYP 240M | 41%SYP2.5B | SYP246M10% | 2027-03-31Expires in 154 days | Guarantee2027-04-30Expires in 184 days | 63 | In progress | |
| PSA/2025/025Maarat al-Numan roads, water & drainage — rehabilitation works | Al-Bunyan Al-Mateen Contracting Co. | SYP4.9BNo variations | 32%SYP1.6B | SYP156.8M10% | 2027-08-31Expires in 307 days | Guarantee2027-09-30Expires in 337 days | 69 | In progress | |
| PSA/2025/023Latakia University technical engineering faculty — construction | Al-Sahel Contracting & Development Co. | SYP3BNo variations | 55%SYP1.6B | SYP162.3M10% | 2027-02-28Expires in 123 days | Guarantee2027-03-30Expires in 153 days | 74 | In progress | |
| PSA/2025/020Government fibre backbone roll-out — Damascus–Homs segment | Modern Networks Telecom Co. | SYP2.7BNo variations | 55%SYP1.5B | SYP148.5M10% | 2027-01-31Expires in 95 days | Guarantee2027-03-02Expires in 125 days | 68 | In progress | |
| PSA/2025/006Homs backup data centre — civil & MEP fit-out | Al-Fayhaa General Contracting Co. | SYP2.4B+3.4%Original SYP 2.3B, approved variations SYP 77.5M | 75%SYP1.8B | SYP179.5M10% | 2026-11-30Expires in 33 days | Guarantee2026-12-30Expires in 63 days | 62 | In progress | |
| PSA/2025/005Qalamoun solar field — PV supply & installation | Alternative Energy Contracting Est. | SYP2BNo variations | 55%SYP1.1B | SYP110.8M10% | 2027-04-30Expires in 184 days | Guarantee2027-05-30Expires in 214 days | 86 | In progress | |
| PSA/2025/002Supply & install lighting, cameras, smart signals and the control room — southern M5 | Modern Networks Telecom Co. | SYP1.5BNo variations | 82%SYP1.3B | SYP125.5M10% | 2026-10-31Expires in 3 days | Insurance2026-10-31Expires in 3 days | 70 | In progress | |
| PSA/2024/022Madinat al-Salam water network — rehabilitation works | Al-Shahbaa Construction & Rehabilitation Co. | SYP1.4BNo variations | 95%SYP1.3B | SYP133M10% | 2026-10-31Expires in 3 days | Guarantee2026-11-30Expires in 33 days | 82 | In progress | |
| PSA/2025/007Unified government e-services platform — build & run | Integrated Digital Solutions Co. | SYP1.3B+4.9%Original SYP 1.2B, approved variations SYP 60M | 66%SYP841.5M | SYP84.2M10% | 2027-03-31Expires in 154 days | Guarantee2027-04-30Expires in 184 days | 71 | In progress | |
| PSA/2025/003Integrated public financial management system — supply & implementation | Integrated Financial & Administrative Systems Co. | SYP1BNo variations | 64%SYP660M | SYP66M10% | 2026-12-31Expires in 64 days | Guarantee2027-01-30Expires in 94 days | 64 | In progress | |
| PSA/2025/012Network & server equipment — backup data centre | Modern Networks Telecom Co. | SYP950MNo variations | 64%SYP612.5M | SYP30.6M5% | 2026-11-30Expires in 33 days | Insurance2027-02-28Expires in 123 days | 72 | In progress | |
| PSA/2025/014Framework agreement — government cloud migration services | National Cloud IT Co. | SYP950MNo variations | 52%SYP495M | SYP24.8M5% | 2027-02-28Expires in 123 days | Insurance2027-05-29Expires in 213 days | 84 | In progress | |
| PSA/2025/024As-Suwayda trunk lines & water network — rehabilitation works | Hauran Construction Co. | SYP825MNo variations | 35%SYP287.5M | SYP28.8M10% | 2027-09-30Expires in 337 days | Guarantee2027-10-30Expires in 367 days | 88 | In progress | |
| PSA/2025/004Cybersecurity programme & SOC delivery | Al-Hisn Cybersecurity Co. | SYP787.5MNo variations | 85%SYP670M | SYP33.5M5% | 2026-12-15Expires in 48 days | Guarantee2027-01-14Expires in 78 days | 91 | In progress | |
| PSA/2024/014Supervision — Darayya replacement housing | Dar Al-Khibra Engineering Consultants | SYP670MNo variations | 45%SYP302.5M | SYP15.1M5% | 2027-09-30Expires in 337 days | Guarantee2027-12-31Expires in 429 days | 83 | In progress | |
| PSA/2024/008Project management & supervision — Hama National Hospital extension | Al-Assi Project Management Group | SYP487.5MNo variations | 68%SYP330M | SYP16.5M5% | 2027-06-30Expires in 245 days | Guarantee2027-09-30Expires in 337 days | 76 | In progress | |
| PSA/2025/010e-Litigation platform Release 2 development | Integrated Digital Solutions Co. | SYP370MNo variations | 85%SYP315M | SYP15.8M5% | 2026-11-30Expires in 33 days | Guarantee2026-12-30Expires in 63 days | 87 | In progress | |
| PSA/2024/005Engineering supervision — Aleppo substations rehabilitation | Al-Assi Project Management Group | SYP365MNo variations | 73%SYP267.5M | SYP13.4M5% | 2027-03-31Expires in 154 days | Guarantee2027-06-30Expires in 245 days | 79 | In progress | |
| PSA/2025/017Data governance & national statistics portal indicators advisory | Al-Raay Management Consulting | SYP355MNo variations | 75%SYP266.3M | SYP13.3M5% | 2026-12-31Expires in 64 days | Guarantee2027-01-30Expires in 94 days | 80 | In progress | |
| PSA/2025/019Ministry of Finance e-archiving system — supply & implementation | Integrated Financial & Administrative Systems Co. | SYP290MNo variations | 90%SYP261M | SYP26.1M10% | 2026-09-30Expired 28 days ago | Guarantee2026-10-30Expires in 2 days | 73 | In progress | |
| PSA/2024/021Supervision — Sheikh Najjar industrial city rehabilitation | Dar Al-Khibra Engineering Consultants | SYP280MNo variations | 41%SYP115M | SYP5.8M5% | 2027-06-30Expires in 245 days | Guarantee2027-09-30Expires in 337 days | 81 | In progress | |
| PSA/2025/015Government services mobile app development | Integrated Digital Solutions Co. | SYP245MNo variations | 62%SYP152.5M | SYP7.6M5% | 2027-01-31Expires in 95 days | Insurance2027-07-30Expires in 275 days | 86 | In progress | |
| PSA/2024/018Supervision — Douma wastewater treatment plant | Dar Al-Khibra Engineering Consultants | SYP235MNo variations | 50%SYP117.5M | SYP5.9M5% | 2027-08-31Expires in 307 days | Guarantee2027-11-30Expires in 398 days | 84 | In progress | |
| PSA/2025/011Government data centre hosting — unified e-services platform | National Cloud IT Co. | SYP230MNo variations | 45%SYP103.5M | SYP00% | 2027-06-30Expires in 245 days | Guarantee2027-06-30Expires in 245 days | 89 | In progress | |
| PSA/2024/012Government HR self-service implementation | Integrated Financial & Administrative Systems Co. | SYP220MNo variations | 100%SYP220M | SYP11M5% | 2025-09-30 | Released | 90 | Closed | |
| PSA/2024/009Digital signature & document e-verification development | Integrated Digital Solutions Co. | SYP172.5MNo variations | 100%SYP172.5M | SYP8.6M5% | 2025-07-31 | Released | 88 | Closed | |
| PSA/2025/013QA & project office support — unified e-services platform | Al-Raay Management Consulting | SYP135MNo variations | 60%SYP81M | SYP4.1M5% | 2027-05-31Expires in 215 days | Guarantee2027-05-31Expires in 215 days | 85 | In progress | |
| PSA/2026/001Digital crop-survey app & field enumerator training | Al-Maarifa Training & Development Co. | SYP122.5MNo variations | 60%SYP73.5M | SYP3.7M5% | 2026-12-31Expires in 64 days | Guarantee2027-03-31Expires in 154 days | 77 | In progress | |
| PSA/2026/003Advisory — preparing the 2026–2028 medium-term plan & governorate plans | Al-Raay Management Consulting | SYP72.5MNo variations | 60%SYP43.5M | SYP2.2M5% | 2026-12-15Expires in 48 days | Guarantee2027-03-15Expires in 138 days | 90 | In progress | |
| Total · 33 | SYP91.7B | SYP49.2B | SYP4.7B |