Al-Shahbaa Construction & Rehabilitation Co.

ContractorOn probationIndex below 55 or 5+ violations

Grade 1 — Buildings & MEP works

Vendor performance index
52−23

Entity average ⁦77⁩

Live contracts
2

of ⁦2⁩ contracts on ⁦2⁩ projects

Live contract value
SYP 10.7B

Paid across all its contracts: SYP 8.1B

Open violations
2

of ⁦6⁩ logged

Open claims
3

SYP 224.5M

Scorecard and vendor index

The seven axes the vendor is rated on each quarter, and its index across all its projects against the entity average.

The seven evaluation axes

Latest evaluation: Q3 2026 · ⁦2026-10-05⁩

The seven evaluation axes
  • Al-Shahbaa Construction & Rehabilitation Co.
  • Entity average
The seven evaluation axes
CategoryAl-Shahbaa Construction & Rehabilitation Co.Entity average
Quality6180
Delivery5074
Schedule adherence4270
Compliance5881
Safety6685
Responsiveness4974
Financial standing3875

Axes against the entity

Change since the Q2 2026 evaluation

  • Quality⁦−4⁩61
  • Delivery⁦−5⁩50
  • Schedule adherence⁦−5⁩42
  • Compliance⁦−5⁩58
  • Safety⁦−4⁩66
  • Responsiveness⁦−2⁩49
  • Financial standing⁦−2⁩38
  • Gold mark: the entity average on each axis (overall index ⁦77⁩)

Vendor performance index across its projects

Eight quarters, against the entity average and the target

  • Al-Shahbaa Construction & Rehabilitation Co.
  • Entity average

AI insight

Al-Shahbaa Construction & Rehabilitation Co.’s index fell ⁦23⁩ points in a year

Weakest on Financial standing, ⁦while holding SYP 10⁩.⁦7B of live contracts⁩. A written corrective plan and a monthly review are advised before any new award.

Confidence⁦83%⁩

Performance by contract and project

Every contract of the vendor with its own performance and its project’s health — the index is built from these.

Violations

Logged: ⁦6⁩ · open: ⁦2⁩

  • Certified financial statement expired

    ComplianceMedium⁦2026-10-16⁩PSA/2024/022

    No penalty
  • Confined-space entry without a permit

    SafetyCritical⁦2026-08-25⁩PSA/2024/003

    SYP1.5MClosed
  • Transformers at the eastern substation commissioned late

    DelayCritical⁦2026-07-06⁩PSA/2024/003

    SYP9.5M
  • Oil leak from a transformer after installation

    QualityHigh⁦2026-05-17⁩PSA/2024/003

    No penaltyClosed
  • Workers not registered for social insurance

    LabourHigh⁦2026-03-22⁩PSA/2024/003

    SYP1MClosed
  • Trunk line laid at a diameter off the approved drawings

    QualityMedium⁦2026-02-11⁩PSA/2024/022

    No penaltyClosed

Risks and claims

Vendor risks, contractual risks on its projects, and its open claims

Vendor file

Registration and compliance documents with their expiry, contact details and the evaluation history.

Registration & compliance documents

Documents expiring within 60 days: ⁦2⁩

DocumentNumberExpiry
Commercial registrationس.ت حلب 10488⁦2027-06-15⁩Expires in 230 days
Tax clearance certificateTX-415685⁦2028-12-31⁩Expires in 795 days
Certified financial statementFC-2026-41565⁦2026-10-15⁩Expired 13 days ago
Social-insurance clearanceSI-884885⁦2026-11-08⁩Expires in 11 days
Not-debarred certificateND-52305⁦2027-03-31⁩Expires in 154 days
Professional union membershipPU-311055⁦2027-06-30⁩Expires in 245 days
Contractor classificationCL-7485⁦2027-08-31⁩Expires in 307 days
ISO 9001 certificateISO9001-21945⁦2027-11-30⁩Expires in 398 days

Registration facts

Commercial registration
س.ت حلب 10488
Tax number
TX-415685
City
Aleppo
Compliance rating
Acceptable
Founded
1,986
Employees
2,450

Account contact

Eng. Karim Al-Ibrahim

Executive Projects Manager

+963 93 117 3390 karim.alibrahim@alshahbaa-construction.sy

Evaluation history

Quarterly evaluation by the project manager or finance

  • 52

    Q3 2026

    ⁦2026-10-05⁩ · Eng. Wael Al-Khawlani

  • 56

    Q2 2026

    ⁦2026-07-01⁩ · Eng. Wael Al-Khawlani

  • 58

    Q1 2026

    ⁦2026-04-01⁩ · Eng. Wael Al-Khawlani

  • 60

    Q4 2025

    ⁦2026-01-01⁩ · Eng. Wael Al-Khawlani

Activity

16 October 2026

  1. Impediment: Eng. Wael Al-Khawlani logged a violation Certified financial statement expired

    2026-10-16 09:00

5 October 2026

  1. Edit: Eng. Wael Al-Khawlani ⁦evaluated the vendor for Q3 2026⁩

    2026-10-05 10:00
    Index ⁦52⁩

25 August 2026

  1. Impediment: Eng. Wael Al-Khawlani logged a violation Confined-space entry without a permit

    2026-08-25 09:00

6 July 2026

  1. Impediment: Eng. Wael Al-Khawlani logged a violation Transformers at the eastern substation commissioned late

    2026-07-06 09:00

1 July 2026

  1. Edit: Eng. Wael Al-Khawlani ⁦evaluated the vendor for Q2 2026⁩

    2026-07-01 10:00
    Index ⁦56⁩

17 May 2026

  1. Impediment: Eng. Wael Al-Khawlani logged a violation Oil leak from a transformer after installation

    2026-05-17 09:00

1 April 2026

  1. Edit: Eng. Wael Al-Khawlani ⁦evaluated the vendor for Q1 2026⁩

    2026-04-01 10:00
    Index ⁦58⁩