AI insight
Modern Networks Telecom Co. is a dependable partner
Strongest on Safety, weakest on Schedule adherence. It holds SYP 5.2B of live contracts with steady performance — a candidate for upcoming framework agreements.
Telecom, networks & security systems — Category A
Entity average 77
of 3 contracts on 3 projects
Paid across all its contracts: SYP 3.4B
of 1 logged
Time extension only
The seven axes the vendor is rated on each quarter, and its index across all its projects against the entity average.
Latest evaluation: Q3 2026 · 2026-10-05
| Category | Modern Networks Telecom Co. | Entity average |
|---|---|---|
| Quality | 76 | 80 |
| Delivery | 70 | 74 |
| Schedule adherence | 63 | 70 |
| Compliance | 79 | 81 |
| Safety | 81 | 85 |
| Responsiveness | 68 | 74 |
| Financial standing | 74 | 75 |
Change since the Q2 2026 evaluation
Vendor performance index across its projects
Eight quarters, against the entity average and the target
AI insight
Strongest on Safety, weakest on Schedule adherence. It holds SYP 5.2B of live contracts with steady performance — a candidate for upcoming framework agreements.
Every contract of the vendor with its own performance and its project’s health — the index is built from these.
PSA/2025/002In progress
Supply & install lighting, cameras, smart signals and the control room — southern M5
Damascus–Daraa Highway (Southern M5) — Lighting & Smart SignalsAt risk
Performance
PSA/2025/012In progress
Network & server equipment — backup data centre
Government Backup Data Centre, Homs — Phase 2At risk
Performance
PSA/2025/020In progress
Government fibre backbone roll-out — Damascus–Homs segment
Government Fibre Backbone — Damascus–Homs SegmentAt risk
Performance
Logged: 1 · open: 0
Excavation without a permit near a gas line
SafetyCritical2026-07-28PSA/2025/020
Vendor risks, contractual risks on its projects, and its open claims
Imported cameras and smart signals arriving late
Medium · Eng. Maher Al-Hamawi
45-day extension — customs clearance of the cameras and signals
Extension of time · Submitted
Registration and compliance documents with their expiry, contact details and the evaluation history.
All documents valid
| Document | Number | Expiry | |
|---|---|---|---|
| Commercial registration | س.ت حلب 31657 | 2027-04-15Expires in 169 days | |
| Tax clearance certificate | TX-409411 | 2028-12-31Expires in 795 days | |
| Certified financial statement | FC-2026-41339 | 2027-04-30Expires in 184 days | |
| Social-insurance clearance | SI-882931 | 2027-01-31Expires in 95 days | |
| Not-debarred certificate | ND-52183 | 2027-03-31Expires in 154 days | |
| Professional union membership | PU-310633 | 2027-06-30Expires in 245 days | |
| Contractor classification | CL-7451 | 2027-08-31Expires in 307 days | |
| ISO 9001 certificate | ISO9001-21167 | 2027-11-30Expires in 398 days |
Quarterly evaluation by the project manager or finance
Q3 2026
2026-10-05 · Eng. Wael Al-Khawlani
Q2 2026
2026-07-01 · Eng. Wael Al-Khawlani
Q1 2026
2026-04-01 · Eng. Wael Al-Khawlani
Q4 2025
2026-01-01 · Eng. Wael Al-Khawlani
Edit: Eng. Wael Al-Khawlani evaluated the vendor for Q3 2026
2026-10-05 10:00Impediment: Eng. Wael Al-Khawlani logged a violation Excavation without a permit near a gas line
2026-07-28 09:00Edit: Eng. Wael Al-Khawlani evaluated the vendor for Q2 2026
2026-07-01 10:00Edit: Eng. Wael Al-Khawlani evaluated the vendor for Q1 2026
2026-04-01 10:00