PSA/2025/012
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
64% of the current value paid
Paid
SYP612.5Mof a current value of SYP 950M
Supply and install network, server and storage equipment for the Homs backup data centre.
Monthly certificates on quantities measured and certified by the consultant, paid within 30 days of approval; the advance is recovered from each certificate.
Payment period
30 days
Retention
5%
Released at final acceptance
Advance payment
0%
Recovered from certificates
Penalty cap
10%
Of the contract value
Defects liability
12 months
After substantial completion
Bar: paid share of the value; gold mark: today
Met: 3 of 4
| Measure | Target | Achieved | Breach penalty |
|---|---|---|---|
| HSE incident notification | within 24 h | 2 reported after 48 h | SYP1.3M |
| Non-conformance close-out | within 14 days | average 9 days | — |
| Monthly progress report | by the 5th of the month | on time | — |
| Actual vs planned manpower | at least 90% | 94% | — |
Integration-ready for the ERP contracts & procurement moduleIntegration-ready
Tender file no. — General Authority for Supply and Provision: 2503950550
The integration layer is in place; data exchange starts once the permissions and interfaces are granted.
Bank guarantees and insurance policies with their expiry