Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
82% of the current value paid
Paid
of a current value of SYP 1.5B
Open claims
1
of 1 claim
Extension days claimed
45 days
If granted, it ends on 2026-12-15
Amounts claimed
None
Extension granted
From earlier claims
Extensions of time, cost claims and disputes
CLM-0009Extension of timeSubmitted
45-day extension — customs clearance of the cameras and signals
Outside the contractor’s control, documented by customs letters