PSA/2024/005
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
73% of the current value paid
Paid
SYP267.5Mof a current value of SYP 365M
Full engineering supervision of the Aleppo substations rehabilitation: design review, material and equipment approvals, measurement, and quality and safety control while the neighbourhoods stay supplied during the works.
Monthly certificates for the approved staff timesheets at the contract unit rates.
Payment period
30 days
Retention
5%
Released at final acceptance
Advance payment
0%
Recovered from certificates
Penalty cap
6%
Of the contract value
Defects liability
Not applicable
After substantial completion
Bar: paid share of the value; gold mark: today
Met: 3 of 3
| Measure | Target | Achieved | Breach penalty |
|---|---|---|---|
| Deliverable turnaround | within 10 working days | average 7 days | — |
| Key staff availability | 100% of approved key staff | 100% | — |
| Monthly report | by the 7th of the month | on time | — |
Integration-ready for the ERP contracts & procurement moduleIntegration-ready
Tender file no. — General Authority for Supply and Provision: 2401360069
The integration layer is in place; data exchange starts once the permissions and interfaces are granted.
Bank guarantees and insurance policies with their expiry