Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SYP 46.3M — if approved the value becomes SYP 1.3B
Total
Increase
Decrease
Original valueVO 1Current value
Where the money is now
66% of the current value paid
66%
Paid
SYP841.5M
of a current value of SYP 1.3B
Retention held(10% of each certificate)
SYP84.2M
Advance not yet recovered(of an advance of SYP 121.5M)
SYP37.4M
Value remaining
SYP433.5M
AI insight
The contract is heading past its end date
Go-live runs 42 days behind plan. The extension claim was assessed at 28 days and the pending variation (SYP 46.25M) adds 21 days; approving both moves the contract end beyond 31 March 2027.
Design, build and run the unified government e-services platform: 68 e-services (civil-registry extracts, «no criminal record» requests, vehicle and property services, building permits from the administrative units, municipal fees, utility subscriptions), identity checks against the civil registry, links to the ministries through the national interoperability framework, and bank e-payment.
Payment terms
Payments against accepted milestones per the payment schedule, within 30 days of the acceptance record.