Unified Government e-Services Platform
Remove from watchlistOne platform for 68 citizen e-services in a single journey — civil-status records, documents, building permits, local fees — checking identity against the civil registry and linking the ministries through the national interoperability framework.
Budget (BAC)
Actual cost
60% of budget
Progress
Estimate at completion
+SYP 90M
SPI · CPI
Forecast finish
42 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure31 March 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started
Finance & earned value
The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.
Budget anatomy
The approved SYP 2.2B split into spent, committed and left, with the estimate at completion
- Actual spendSYP 1.3B
- Committed, not spentSYP 490M
- Allotted, uncommittedSYP 312.5M
- Contingency availableSYP 52.5M
Budget
- EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
- SYP 2B
- Original budgetwhen the first baseline was approved
- SYP 2.1B
- Approved budgetafter approved change requests
- SYP 2.2B
- Current budgetavailable to spend now
- SYP 2.2B
- Revised budgetif the pending changes are approved
- SYP 2.3B
Commitments
- CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
- SYP 1.8B
- Contracts3 active contracts
- SYP 1.6B
- Purchase orders3 orders
- SYP 155M
- Remaining budgetapproved less actual
- SYP 855M
Spend & outlook
- Actual costSyncedFrom the nightly finance-system syncincluding accruals
- SYP 1.3B
- Accrualswork done, not yet invoiced
- SYP 59M
- Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
- SYP 2.3B
- ContingencySYP 27.5M drawn of SYP 80M
- SYP 52.5M
Estimated vs approved budget
What the project proposal estimated before approval, against today’s approved budget and the estimate at completion
- Approved is SYP 195M (9.9%) above the estimate
- The estimate at completion is SYP 285M (14.5%) above the estimate
From the «project proposal & feasibility study» approved at the approval gate on 2024-09-22 · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.
ERP link — data readiness
The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system
- Cost centreCC-61014
- WBS elements7 elements · P-2026-014.01 …
- Purchase orders3 synced · 0 manual
- Invoices & certificates28 posted · 1 in approval
Where each figure comes from
- EstimatedManualFrom the project proposal — not from the finance system
- CommitmentsSyncedFrom the nightly finance-system sync
- Actual costSyncedFrom the nightly finance-system sync
- Estimate at completionManualThe project manager’s estimate — not from the finance system
Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.
Purchase-order registerManual edit log
Every manual update — who, when, why and from which source
| Date | By | Figure | From → to | Reason | Source |
|---|---|---|---|---|---|
| 2026-10-0510:20 | Omar Al-NahhasOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.sy | Actual spend | SYP 1.3BSYP 1.3B | September government data centre hosting accruals posted before the finance system transferred them | Finance department monthly reportFIN-RPT-2026-09 |
| 2026-09-3013:05 | Eng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.sy | Estimate at completion | SYP 2.2BSYP 2.3B | Re-estimated after the late first wave and a two-month extension of the integration team | Project manager’s estimate |
| 2026-08-1209:40 | Omar Al-NahhasOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.sy | Commitments | SYP 1.7BSYP 1.8B | Security scanning tools order added before the sync completed | Export from the finance system (ERP)PO-2026-0812 |
Budget bridge
From the original to the revised request
- Total
- Increase
- Decrease
Contingency draw-downs
SYP 27.5M drawn of SYP 80M
- Civil-registry integration — extra test environment2026-03-18SYP 10.5M
- Fee services — fee calculator linked to e-payment2026-06-09SYP 9.5M
- Data migration — cleansing old transaction records2026-09-22SYP 7.5M
Purchase orders
- PO-2026-0812Security & application scanning toolsSYP 60MSYP 20M paid
- PO-2025-0634Identity & access management licencesSYP 65MSYP 65M paid
- PO-2025-0118Project office advisory — first six monthsSYP 30MSYP 30M paid
Cost breakdown structure
Every dimension adds up to the same totals
| Item | BudgetSYP M | CommittedSYP M | ActualSYP M | EACSYP M | VarianceSYP M | Consumption |
|---|---|---|---|---|---|---|
| 1Project management & governance | 168.60 | 150.72 | 123.12 | 174.87 | −6.27 | |
| 2Requirements & government e-service design | 252.90 | 257.81 | 257.81 | 257.81 | −4.91 | |
| 3Core platform build | 632.25 | 581.56 | 503.30 | 650.03 | −17.78 | |
| 4National systems & agency integration | 379.35 | 300.13 | 177.83 | 407.14 | −27.79 | |
| 5Data migration | 210.75 | 167.47 | 100.66 | 225.93 | −15.18 | |
| 6Testing, quality & security | 252.90 | 193.58 | 102.01 | 273.71 | −20.81 | |
| 7Launch & change management | 210.75 | 143.73 | 40.27 | 234.26 | −23.51 | |
| Unallocated contingency | 52.50 | 0.00 | 0.00 | 26.25 | +26.25 | |
| Total | 2,160.00 | 1,795.00 | 1,305.00 | 2,250.00 | −90.00 |
Budget split
WBS
SYP 2.2B
Budget
- Project management & governanceSYP 168.6M8%
- Requirements & government e-service designSYP 252.9M12%
- Core platform buildSYP 632.3M29%
- National systems & agency integrationSYP 379.4M18%
- Data migrationSYP 210.7M10%
- Testing, quality & securitySYP 252.9M12%
- Launch & change managementSYP 210.8M10%
- Unallocated contingencySYP 52.5M2%
Cash flow
Planned, committed, actual and forecast
Spend per period
SYP millions
- Planned
- Actual
- Forecast
Cumulative S-curve
Cumulative to close
- Actual, then forecast
- Planned, cumulative
- Committed, cumulative
- Forecast
Earned value management
At the data date 2026-10-28
Planned value, earned value and actual cost
- Planned value
- Earned value
- Actual cost
- Estimate at completion
- Budget at completion
0.87
Off track
Schedule performance index
SPI = EV ÷ PV
0.96
On track
Cost performance index
CPI = EV ÷ AC
Finish by earned schedule
2027-06-27+88
SPI(t) 0.90 against the approved finish 2027-03-31
- Planned valuePV
- SYP 1.4B
- The value of the work that should be done by today.
- PV
- Earned valueEV
- SYP 1.3B
- The value of the work actually done, at plan prices.
- EV = % complete × BAC
- Actual costAC
- SYP 1.3B
- What has actually been spent on the work done.
- AC
- Budget at completionBAC
- SYP 2.2B
- The approved budget for the whole project.
- BAC
- Cost varianceCV
- −52.20 SYP M
- Earned less actual; negative means paying more than the value.
- CV = EV − AC
- Schedule varianceSV
- −194.40 SYP M
- Earned less planned; negative means behind, in value.
- SV = EV − PV
- Cost performance indexCPI
- 0.96
- Value produced per pound spent; under 1 is an overrun.
- CPI = EV ÷ AC
- Schedule performance indexSPI
- 0.87
- Work done over work planned; under 1 is behind.
- SPI = EV ÷ PV
- Estimate at completionEAC
- SYP 2.3B
- What the project will cost when it finishes, as forecast.
- EAC = BAC ÷ CPI
- Estimate to completeETC
- SYP 945M
- What is still to be spent to completion.
- ETC = EAC − AC
- Variance at completionVAC
- −90.00 SYP M
- Budget less the estimate; negative is an overrun.
- VAC = BAC − EAC
- To-complete performance indexTCPI
- 1.06
- The cost efficiency the rest must reach to stay on budget.
- TCPI = (BAC − EV) ÷ (BAC − AC)
Automatic end-of-project forecast
Four ways to estimate the final cost, and the date earned schedule points to
- At today’s cost performanceSYP 2.3B
- If the rest goes to planSYP 2.2B
- At cost and schedule performanceSYP 2.4B
- The PM’s bottom-up estimateSYP 2.3B
- To stay within SYP 2.2B, cost performance on the rest must rise to 1.06 — above what has been achieved.
Estimate at completion at that performance
SYP 2.3B
Variance at completion: −90.00 SYP M