PRJ-2026-014At risk4ExecutionHybridIn progressDelivered by:Ministry of Communications and Information Technology

Unified Government e-Services Platform

Remove from watchlist

One platform for 68 citizen e-services in a single journey — civil-status records, documents, building permits, local fees — checking identity against the civil registry and linking the ministries through the national interoperability framework.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 2.2B

Actual cost

SYP 1.3B

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SYP 2.3B

+SYP 90M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SYP 2.2B split into spent, committed and left, with the estimate at completion

Forecast overrun SYP 90M
EAC SYP 2.3B
Revised request SYP 2.3B
  • Actual spendSYP 1.3B
  • Committed, not spentSYP 490M
  • Allotted, uncommittedSYP 312.5M
  • Contingency availableSYP 52.5M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SYP 2B
Original budgetwhen the first baseline was approved
SYP 2.1B
Approved budgetafter approved change requests
SYP 2.2B
Current budgetavailable to spend now
SYP 2.2B
Revised budgetif the pending changes are approved
SYP 2.3B

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SYP 1.8B
Contracts3 active contracts
SYP 1.6B
Purchase orders⁦3⁩ orders
SYP 155M
Remaining budgetapproved less actual
SYP 855M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SYP 1.3B
Accrualswork done, not yet invoiced
SYP 59M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SYP 2.3B
ContingencySYP 27.5M drawn of SYP 80M
SYP 52.5M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSYP 2B
ApprovedSYP 2.2B
Estimate at completionSYP 2.3B
Approved is SYP 195M (⁦9.9%⁩) above the estimate
The estimate at completion is SYP 285M (⁦14.5%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2024-09-22⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-61014
  • WBS elements⁦7⁩ elements · P-2026-014.01 …
  • Purchase orders⁦3⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦28⁩ posted · ⁦1⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

Manual edit log
DateByFigureFrom → toReasonSource
⁦2026-10-05⁩10:20Omar Al-NahhasOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syActual spendSYP 1.3BSYP 1.3BSeptember government data centre hosting accruals posted before the finance system transferred themFinance department monthly reportFIN-RPT-2026-09
⁦2026-09-30⁩13:05Eng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.syEstimate at completionSYP 2.2BSYP 2.3BRe-estimated after the late first wave and a two-month extension of the integration teamProject manager’s estimate
⁦2026-08-12⁩09:40Omar Al-NahhasOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syCommitmentsSYP 1.7BSYP 1.8BSecurity scanning tools order added before the sync completedExport from the finance system (ERP)PO-2026-0812

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SYP 27.5M drawn of SYP 80M

  • Civil-registry integration — extra test environment⁦2026-03-18⁩SYP 10.5M
  • Fee services — fee calculator linked to e-payment⁦2026-06-09⁩SYP 9.5M
  • Data migration — cleansing old transaction records⁦2026-09-22⁩SYP 7.5M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSYP MCommittedSYP MActualSYP MEACSYP MVarianceSYP MConsumption
1Project management & governance168.60150.72123.12174.87⁦−6.27⁩
2Requirements & government e-service design252.90257.81257.81257.81⁦−4.91⁩
3Core platform build632.25581.56503.30650.03⁦−17.78⁩
4National systems & agency integration379.35300.13177.83407.14⁦−27.79⁩
5Data migration210.75167.47100.66225.93⁦−15.18⁩
6Testing, quality & security252.90193.58102.01273.71⁦−20.81⁩
7Launch & change management210.75143.7340.27234.26⁦−23.51⁩
Unallocated contingency52.500.000.0026.25⁦+26.25⁩
Total2,160.001,795.001,305.002,250.00⁦−90.00⁩

Budget split

WBS

SYP 2.2B

Budget

  • Project management & governanceSYP 168.6M⁦8%⁩
  • Requirements & government e-service designSYP 252.9M⁦12%⁩
  • Core platform buildSYP 632.3M⁦29%⁩
  • National systems & agency integrationSYP 379.4M⁦18%⁩
  • Data migrationSYP 210.7M⁦10%⁩
  • Testing, quality & securitySYP 252.9M⁦12%⁩
  • Launch & change managementSYP 210.8M⁦10%⁩
  • Unallocated contingencySYP 52.5M⁦2%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SYP millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-06-27⁩+88

SPI(t) ⁦0.90⁩ against the approved finish ⁦2027-03-31⁩

Planned valuePV
SYP 1.4B
The value of the work that should be done by today.
PV
Earned valueEV
SYP 1.3B
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SYP 1.3B
What has actually been spent on the work done.
AC
Budget at completionBAC
SYP 2.2B
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−52.20⁩ SYP M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−194.40⁩ SYP M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.96
Value produced per pound spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.87
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SYP 2.3B
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SYP 945M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−90.00⁩ SYP M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.06
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSYP 2.3B
  • If the rest goes to planSYP 2.2B
  • At cost and schedule performanceSYP 2.4B
  • The PM’s bottom-up estimateSYP 2.3B
  • To stay within SYP 2.2B, cost performance on the rest must rise to ⁦1.06⁩ — above what has been achieved.

Estimate at completion at that performance

SYP 2.3B

Variance at completion: ⁦−90.00⁩ SYP M