Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-014At risk4ExecutionHybridIn progressDelivered by:Ministry of Communications and Information Technology

Unified Government e-Services Platform

Remove from watchlist

One platform for 68 citizen e-services in a single journey — civil-status records, documents, building permits, local fees — checking identity against the civil registry and linking the ministries through the national interoperability framework.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 2.2B

Actual cost

SYP 1.3B

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SYP 2.3B

+SYP 90M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
PSA-PMO-F05
Template edition
2.0
Version
V3
Form date
⁦2025-01-30⁩
ApprovedPRJ-2026-014Unified Government e-Services Platform

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-014
Project
Unified Government e-Services Platform
Portfolio
Digital Government Services & Data Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Khaled Al-Kayyali
Project manager
Eng. Tarek Al-Mardini

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2025-01-05⁩

Baseline finish

⁦2027-03-31⁩

Forecast finish

⁦2027-05-12⁩

SPI

0.87

MilestonePlannedForecastSlip
Charter approved⁦2025-01-05⁩⁦2025-01-05⁩0
Build & run contract signed⁦2025-04-30⁩⁦2025-05-04⁩+4 days
Advance payment (10%) released⁦2025-05-25⁩⁦2025-06-01⁩+7 days
Requirements & design signed off⁦2025-09-30⁩⁦2025-10-21⁩+21 days
Internal pilot (MVP) live⁦2026-03-31⁩⁦2026-04-28⁩+28 days
Data classification approved under the data-protection policy⁦2026-06-30⁩⁦2026-07-14⁩+14 days
Wave 1 development complete (24 services)⁦2026-09-30⁩⁦2026-11-12⁩+43 days
Civil registry & national interoperability integration complete⁦2026-10-31⁩⁦2026-12-10⁩+40 days
Penetration test passed, security sign-off⁦2026-12-15⁩⁦2027-01-28⁩+44 days
User acceptance testing complete⁦2027-01-31⁩⁦2027-03-14⁩+42 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Business requirements document⁦10%⁩⁦2025-08-31⁩Hiba Al-Shami
UX prototype⁦6%⁩⁦2025-09-15⁩Yasmine Bitar
Solution & integration design⁦6%⁩⁦2026-10-15⁩Eng. Rita Ghanem
Wave 1 service package (24 services)⁦14%⁩⁦2026-09-30⁩Eng. Tarek Al-Mardini
Civil-registry identity-check interfaces⁦5%⁩⁦2026-10-31⁩Hamza Al-Hussein
National interoperability framework interfaces⁦5%⁩⁦2026-11-15⁩Hamza Al-Hussein
Data migration plan⁦3%⁩⁦2026-10-10⁩Moaz Kaddour
Master test plan⁦4%⁩⁦2026-06-30⁩Joud Hammami
Performance & load test report⁦3%⁩⁦2026-12-20⁩Eng. Saleh Al-Bakir
Change management & training plan⁦3%⁩⁦2026-10-31⁩Ola Al-Jandali
User & operator guide⁦3%⁩⁦2027-02-15⁩Hiba Al-Shami
Internal pilot: the core platform and three services⁦30%⁩⁦2026-03-31⁩Eng. Tarek Al-Mardini
Approved service-data classification register⁦8%⁩⁦2026-06-30⁩Moaz Kaddour
Accepted with a certificate⁦58%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0001Civil-registry identity and interoperability interfaces not ready on time16MitigateEng. Tarek Al-Mardini
RSK-0002Shortage of integration and back-end engineers on the vendor team16EscalateEng. Tarek Al-Mardini
RSK-0003Late sign-off of service requirements by the owning ministries12MitigateEng. Lina Al-Attar
RSK-0006Possible critical findings in the pre-launch penetration test12MitigateEng. Hussam Zeidan
RSK-0005Incomplete migration of open-request data from the ministries’ current systems9MitigateMoaz Kaddour
RSK-0007Citizen service centre staff resisting the new digital procedures9MitigateOla Al-Jandali
RSK-0009Reusing digital-signature components to shorten development9AcceptEng. Tarek Al-Mardini
RSK-0010Mobile-app team competing with the platform for the same people9MitigateEng. Lina Al-Attar

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
National Steering CommitteeOverall status, variances, decisions neededMonthlyEng. Tarek Al-Mardini
Project sponsorThe periodic update card and top five risksWeeklyEng. Tarek Al-Mardini
Change CommitteeChange requests and impact analysisWeeklyEng. Tarek Al-Mardini
Service-owning ministries and governorate centresPending requirements and sprint demosFortnightlyHiba Al-Shami
Ministry of Administrative DevelopmentRelease plan and service-simplification statusAt each milestoneHiba Al-Shami
Ministry of Interior — Civil RegistryEnvironment readiness and integration issuesWeeklyHamza Al-Hussein
Citizen service centre staffWhat changes in their work, training datesMonthlyOla Al-Jandali
Citizens and residentsNew e-services and launch datesAt each milestoneOla Al-Jandali
Team memberRoleAllocation
Eng. Tarek Al-MardiniProject manager⁦100%⁩
Eng. Lina Al-AttarProgramme manager (oversight)⁦20%⁩
Eng. Khaled Al-KayyaliProject sponsor⁦20%⁩
Ibrahim Al-SaeedProject owner⁦15%⁩
Hamza Al-HusseinLead integration engineer⁦100%⁩
Hiba Al-ShamiSenior business analyst⁦80%⁩
Joud HammamiQA & test lead⁦70%⁩
Ola Al-JandaliChange management specialist⁦30%⁩

5QualityAuto-filled

Quality leadAuto-filled
Joud Hammami
Review cadenceAuto-filled
A code review each sprint; acceptance testing with each services wave
Next reviewAuto-filled
⁦2026-11-04⁩
Quality criterionThresholdNowMet
Automated test coverage70% or more per module58% (agency-integration module 48%)No
AccessibilityZero critical findings6 findings on the e-service request formsNo
High-severity vulnerabilitiesZero before launchZero in the last scanYes
Page response timeUnder 2 s for 95% of requests1.4 sYes

6BenefitsAuto-filled

BenefitBaselineTargetOwner
Higher citizen satisfaction with digital government services68 %88 %Basel Al-Mahayni
Lower cost per e-service transaction2300 SYP / transaction900 SYP / transactionBasel Al-Mahayni
Shorter time for transactions that need checking21 days5 daysEng. Lina Al-Attar

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformSubmitted—⁦2025-01-30⁩ 09:54
2Methodology review — PMOMethodology reviewMariam Al-ZoubiPMO — analystApprovedComplete against the project management plan template.⁦2025-02-04⁩ 11:26
3Technical acceptance — project ownerTechnical acceptanceIbrahim Al-SaeedProject ownerApproved—⁦2025-02-05⁩ 12:33
4Cash flow & financial commitmentFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-02-09⁩ 10:49
5Plan aligned with the contractsFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2025-02-10⁩ 11:26
6Sponsor approvalTechnical acceptanceEng. Khaled Al-KayyaliProject sponsorApproved—⁦2025-02-11⁩ 09:54

Signatures

Methodology review — PMO

Mariam Al-Zoubi

Approved⁦2025-02-04⁩

Technical acceptance — project owner

Ibrahim Al-Saeed

Approved⁦2025-02-05⁩

Cash flow & financial commitment

Rasha Al-Mudarres

Approved⁦2025-02-09⁩

Plan aligned with the contracts

Abdullah Al-Ujaili

Approved⁦2025-02-10⁩

Sponsor approval

Eng. Khaled Al-Kayyali

Approved⁦2025-02-11⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F05 · version V3

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Tarek Al-Mardini on ⁦2025-01-30⁩

  1. Methodology review

    Methodology review — PMO

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-02-04⁩ at ⁦11:26⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Ibrahim Al-Saeed · Project owner

    Approved · ⁦2025-02-05⁩ at ⁦12:33⁩

  3. Financial approval

    Cash flow & financial commitment

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-02-09⁩ at ⁦10:49⁩

  4. Financial approval

    Plan aligned with the contracts

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-02-10⁩ at ⁦11:26⁩

  5. Technical acceptance

    Sponsor approval

    Eng. Khaled Al-Kayyali · Project sponsor

    Approved · ⁦2025-02-11⁩ at ⁦09:54⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V3ApprovedCurrent⁦2026-03-02⁩

    Updated after CR-2026-004; three services moved to wave 2

    • Schedule: wave 1 now 24 services instead of 27
    • Communications: a weekly report to the Steering Committee

    Eng. Tarek Al-Mardini

  2. V2Approved⁦2025-01-30⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Tarek Al-Mardini

  3. V1Returned for edit⁦2025-01-16⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Eng. Tarek Al-Mardini

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close