RSK-0005Unified Government e-Services Platform

Incomplete migration of open-request data from the ministries’ current systems

9MediumOpen

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Uneven quality of open-request data in the ministries’ legacy systems, and no clear owner for some tables

Preventive controls

  • Cleanse the data before migration under the approved data-protection policy
  • Trial migration of 10% of the requests in one governorate

2 / 2

Event

Incomplete migration of open-request data from the ministries’ current systems

9MediumTrigger

An error rate above 2% in the trial migration

Contingency

Run the legacy systems in parallel for open requests for three months after launch

Impact

Errors in transaction records and their status, and a later wave 1

SYP 18.8M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
9Medium

Residual

5
4
3
2
1
1
2
3
4
5
4Low

Exposure

SYP 18.8M

Residual

⁦56⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 7 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Eng. Tarek Al-Mardini

    Currently followed up here
  2. 2

    Programme manager

    Eng. Lina Al-Attar

  3. 3

    PMO director

    Dr. Reem Al-Qabbani

  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • Cleanse the data before migration under the approved data-protection policy

    Moaz KaddourMoaz KaddourData EngineerP-032moaz.kaddour@psa.gov.sy
    In progressIn 23 days2026-11-20
  • Trial migration of 10% of the requests in one governorate

    Moaz KaddourMoaz KaddourData EngineerP-032moaz.kaddour@psa.gov.sy
    Not startedIn 8 days2026-11-05

Trigger

An error rate above 2% in the trial migration

Contingency

Run the legacy systems in parallel for open requests for three months after launch