Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-014At risk4ExecutionHybridIn progressDelivered by:Ministry of Communications and Information Technology

Unified Government e-Services Platform

Remove from watchlist

One platform for 68 citizen e-services in a single journey — civil-status records, documents, building permits, local fees — checking identity against the civil registry and linking the ministries through the national interoperability framework.

Early warning: ⁦74%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 2.2B

Actual cost

SYP 1.3B

⁦60%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦23%⁩

Estimate at completion

SYP 2.3B

+SYP 90M

SPI · CPI

0.87Schedule performance index · 0.870.96Cost performance index · 0.96

Forecast finish

⁦2027-05-12⁩

42 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure31 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate22 September 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate5 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 April 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate31 March 2027Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

AI insight

⁦74%⁩ chance of a further slip within ⁦45⁩ days

From the SPI trend (⁦0.87⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is at risk: ⁦58% done against 67% planned⁩; ⁦official launch now forecast for 12 May 2027 instead of 31 March⁩.

The main cause is the vendor’s integration-engineer gap and a nine-day civil-registry test-environment outage, ⁦which pushed back the wave-1 and integration milestones⁩.

Cost is broadly in control (⁦CPI 0⁩.⁦96⁩); ⁦EAC SYP 2⁩.⁦25bn⁩, SYP ⁦90M over⁩.

Needed: ⁦approve CR-2026-012 for extra integration capacity⁩ — ⁦it recovers 12 days⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Governance & Digital TransformationSO-5.1Integrated digital government services for citizens

Main initiative

SI-5.1.1Unified government services

Contribution to the initiative⁦81%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

Annual work-plan line
WP-2025-014
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦58%⁩

Awaiting acceptance ⁦23%⁩

Not handed in ⁦19%⁩

5 deliverables accepted

  • Internal pilot: the core platform and three services⁦30%⁩
  • Business requirements document⁦10%⁩
  • Approved service-data classification register⁦8%⁩
  • UX prototype⁦6%⁩
  • Master test plan⁦4%⁩

3 deliverables under inspection or acceptance

  • Wave 1 service package (24 services)⁦14%⁩
  • Solution & integration design⁦6%⁩
  • Change management & training plan⁦3%⁩

Corrective planCP-2026-01

Awaiting approvalOverdue: ⁦1⁩

Civil-registry and interoperability interfaces 40 days late, two vendor integration engineers withdrawn, and conflicting civil-status extract requirements between the governorate offices

Actions

⁦1⁩ of ⁦6⁩ done

Next: Approve a phased integration test plan instead of one big-bang test · Joud Hammami · 2026-10-25

Days won back

⁦6⁩ of ⁦21⁩

With the plan: 2027-05-12

Open the plan

Progress & earned value

⁦6⁩ of ⁦12⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦83%⁩ of budget

SYP1.3B/ SYP2.2BSYP90Mprojected overrun(⁦4.2%⁩)
Actual spend
SYP1.3B
Committed
SYP1.8B
Approved budget
SYP2.2B
Estimate at completion
SYP2.3B

Next milestones

  • Wave 1 development complete (24 services)⁦2026-11-12⁩was ⁦2026-09-30⁩Late
  • Civil registry & national interoperability integration complete⁦2026-12-10⁩was ⁦2026-10-31⁩Late
  • Penetration test passed, security sign-off⁦2027-01-28⁩was ⁦2026-12-15⁩At risk
  • User acceptance testing complete⁦2027-03-14⁩was ⁦2027-01-31⁩At risk
  • Official launch of the unified government e-services platform⁦2027-04-15⁩was ⁦2027-03-01⁩At risk

Waiting on someone

⁦14⁩ approvals and ⁦6⁩ open actions on this project

Approvals & requests

From «My actions» for this project

Actions

⁦6⁩ open

  • Vendor to submit a replacement plan for integration engineers within a weekEng. Tarek Al-MardiniIn 5 days2026-11-02High
  • Ask the Ministry of Interior to extend the civil-registry test environmentEng. Lina Al-AttarDue tomorrow2026-10-29High
  • ⁦Lift automated test coverage to 75% before UAT⁩Joud HammamiIn 23 days2026-11-20Medium
  • Align the civil-record extract service in a joint workshop with the governorate officesHiba Al-ShamiIn 2 days2026-10-30Medium
  • Prepare a load-test plan for the hosting environmentEng. Saleh Al-BakirIn 18 days2026-11-15Medium
  • Update the corrective plan and present it to the Steering CommitteeEng. Tarek Al-MardiniIn 4 days2026-11-01High

Risks & impediments

11 open risks, exposure SYP 258.8M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩2Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0001Civil-registry identity and interoperability interfaces not ready on timeRSK-0002Shortage of integration and back-end engineers on the vendor teamProbability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩3Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0005Incomplete migration of open-request data from the ministries’ current systemsRSK-0007Citizen service centre staff resisting the new digital proceduresRSK-0010Mobile-app team competing with the platform for the same people2Probability: Possible · Impact: MajorMedium · Score ⁦12⁩RSK-0003Late sign-off of service requirements by the owning ministriesRSK-0006Possible critical findings in the pre-launch penetration testProbability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩2Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩RSK-0008Late delivery of identity & access management licencesRSK-0011Updated government-services UX guide from the Ministry of Communications1Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩RSK-0004Government data centre hosting capacity exceeded at launchProbability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High2
  • Medium6
  • Low2

Deliverables

⁦5⁩ of ⁦13⁩ approved

  • Business requirements documentDLV-01 · V4 · CRT-014-01⁦10%⁩Hiba Al-Shami2025-08-312025-08-31Approved
  • UX prototypeDLV-02 · V3 · CRT-014-02⁦6%⁩Yasmine Bitar2025-09-152025-09-15Approved
  • Solution & integration designDLV-03 · V5⁦6%⁩Eng. Rita Ghanem13 days overdue2026-10-15In review
  • Wave 1 service package (24 services)DLV-04 · V1⁦14%⁩Eng. Tarek Al-Mardini28 days overdue2026-09-30Submitted
  • Civil-registry identity-check interfacesDLV-05 · V2⁦5%⁩Hamza Al-HusseinIn 3 days2026-10-31Draft
  • National interoperability framework interfacesDLV-06 · V1⁦5%⁩Hamza Al-HusseinIn 18 days2026-11-15Draft
  • Data migration planDLV-07 · V2⁦3%⁩Moaz Kaddour18 days overdue2026-10-10Returned
  • Master test planDLV-08 · V3 · CRT-014-08⁦4%⁩Joud Hammami2026-06-302026-06-30Approved
  • Performance & load test reportDLV-09 · V0⁦3%⁩Eng. Saleh Al-BakirIn 53 days2026-12-20Draft
  • Change management & training planDLV-10 · V2⁦3%⁩Ola Al-JandaliIn 3 days2026-10-31Submitted
  • User & operator guideDLV-11 · V0⁦3%⁩Hiba Al-ShamiIn 110 days2027-02-15Draft
  • Internal pilot: the core platform and three servicesDLV-12 · V2 · CRT-014-12⁦30%⁩Eng. Tarek Al-Mardini2026-03-312026-03-31Approved
  • Approved service-data classification registerDLV-13 · V2 · CRT-014-13⁦8%⁩Moaz Kaddour2026-06-302026-06-30Approved

Team, contracts & documents

Team

16 members

Eng. Tarek Al-Mardini · Project Manager, Unified Government e-Services PlatformEng. Lina Al-Attar · Head of the Unified Government e-Services Platform & Programme Manager, Government e-ServicesEng. Khaled Al-Kayyali · Deputy President, Digital TransformationIbrahim Al-Saeed · Director General, Government Services in the GovernoratesHamza Al-Hussein · Senior Software Engineer – IntegrationHiba Al-Shami · Senior Business Analyst — Government ServicesJoud Hammami · QA & Testing Specialist
  • Eng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformProject managerP-005tarek.almardini@psa.gov.sy⁦100%⁩
  • Eng. Lina Al-AttarEng. Lina Al-AttarHead of the Unified Government e-Services Platform & Programme Manager, Government e-ServicesProgramme manager (oversight)P-004lina.alattar@psa.gov.sy⁦20%⁩
  • Eng. Khaled Al-KayyaliEng. Khaled Al-KayyaliDeputy President, Digital TransformationProject sponsorP-011khaled.alkayyali@psa.gov.sy⁦20%⁩
  • Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesProject ownerP-046ibrahim.alsaeed@psa.gov.sy⁦15%⁩
  • Hamza Al-HusseinHamza Al-HusseinSenior Software Engineer – IntegrationLead integration engineerP-030hamza.alhussein@psa.gov.sy⁦100%⁩
  • Hiba Al-ShamiHiba Al-ShamiSenior Business Analyst — Government ServicesSenior business analystP-006hiba.alshami@psa.gov.sy⁦80%⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close