AI insight
74% chance of a further slip within 45 days
From the SPI trend (0.87), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
One platform for 68 citizen e-services in a single journey — civil-status records, documents, building permits, local fees — checking identity against the civil registry and linking the ministries through the national interoperability framework.
Budget (BAC)
Actual cost
60% of budget
Progress
Estimate at completion
+SYP 90M
SPI · CPI
Forecast finish
42 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure31 March 2027
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
69
Needs watching
Index over the last six reports
May to October 2026
AI insight
From the SPI trend (0.87), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
Generated from the live project data
The project is at risk: 58% done against 67% planned; official launch now forecast for 12 May 2027 instead of 31 March.
The main cause is the vendor’s integration-engineer gap and a nine-day civil-registry test-environment outage, which pushed back the wave-1 and integration milestones.
Cost is broadly in control (CPI 0.96); EAC SYP 2.25bn, SYP 90M over.
Needed: approve CR-2026-012 for extra integration capacity — it recovers 12 days.
How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.
The main objective and initiative, the secondary links, and the project’s contribution to its initiative.
Main initiative
SI-5.1.1Unified government services
The project’s share of the initiative’s project budget (3 projects)
Secondary links
Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.
Counted
58%Awaiting acceptance 23%
Not handed in 19%
5 deliverables accepted
3 deliverables under inspection or acceptance
Corrective planCP-2026-01
Awaiting approvalOverdue: 1
Civil-registry and interoperability interfaces 40 days late, two vendor integration engineers withdrawn, and conflicting civil-status extract requirements between the governorate offices
Actions
1 of 6 done
Next: Approve a phased integration test plan instead of one big-bang test · Joud Hammami · 2026-10-25
Days won back
6 of 21
With the plan: 2027-05-12
6 of 12 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 83% of budget
14 approvals and 6 open actions on this project
From «My actions» for this project
6 open
Cost and schedule impact
11 open risks, exposure SYP 258.8M
Impact
2 escalated
5 of 13 approved
16 members
Team
16 members
3 contracts