Project status report — October 2026

InternalSubmittedV1

October status report: ⁦58% complete against 67% planned⁩, ⁦SPI 0⁩.⁦87⁩, risks and the decisions needed.

More

Internal

Syrian Arab Republic

Planning and Statistics Authority

National Project Management Office (PMO)

Code
DOC-0204
Version
V1
Date
2026-10-27

Project status report — ⁦October 2026⁩

Unified Government e-Services Platform

⁦1⁩. Executive summary

This report gives the position of Unified Government e-Services Platform to date: ⁦58% complete against 67% planned⁩, ⁦SPI 0⁩.⁦87⁩, ⁦CPI 0⁩.⁦96⁩, ⁦and an estimate at completion of SYP 2⁩.⁦25bn⁩.

Project
Unified Government e-Services Platform (⁦PRJ-2026-014⁩)
Project manager
Eng. Tarek Al-Mardini
Budget
⁦SYP 2⁩.⁦16bn⁩
Progress
⁦58% actual against 67% planned⁩
Forecast finish
⁦2027-05-12⁩

⁦2⁩. Key findings

  • All planned milestones of the period met except one deferred
  • Actual spend rose in line with the work done
  • Three high risks under treatment, each with a named owner

⁦3⁩. Recommendations & decisions needed

  • Approve the proposed treatment of the high risks
  • Track the open findings with the vendor weekly

Prepared by

Eng. Tarek Al-Mardini
Issued from Munjaz — valid only once approved electronically1 / 1