CP-2026-01Version 2
Unified Government e-Services Platform
One corrective plan: why the project slipped, the rule that triggered it, the actions, the days won back, approval and follow-up.
What triggered the plan
The project’s reading the day the rule fired, and today.
Detected on 2026-08-31
Slip past the baseline
- At detection
- 48 days
- Today
- 42 days
- Limit
- > 40
Schedule performance index
- At detection
- 0.85
- Today
- 0.87
- Limit
- < 0.85
A rule approved by the Project Approval Committee (PMO-2026/14), read automatically from the project’s data.
Days won back
The forecast finish without the plan, with it, and the difference.
Baseline
2027-03-31Without the plan
2027-06-02+63 days
With the plan
2027-05-12+42 days
Wins back 21 days
Achieved so far: 6 days
Why it slipped
Civil-registry and interoperability interfaces 40 days late, two vendor integration engineers withdrawn, and conflicting civil-status extract requirements between the governorate offices
Corrective actions
Each action with its owner, date, status and the days it wins back; overdue ones are shaded.
Replace four vendor integration engineers, named and dated
Eng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.syACT-0301In progressIn 5 days2026-11-02Wins back 4 daysAdd three integration engineers for four months through a change request
Eng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.syCR-2026-012In progressIn 12 days2026-11-09Wins back 6 daysA dedicated Ministry of Interior test environment for three months
Hamza Al-HusseinHamza Al-HusseinSenior Software Engineer – IntegrationP-030hamza.alhussein@psa.gov.syIn progressIn 7 days2026-11-04Wins back 3 daysMove three services from wave 1 to wave 2
Eng. Lina Al-AttarEng. Lina Al-AttarHead of the Unified Government e-Services Platform & Programme Manager, Government e-ServicesP-004lina.alattar@psa.gov.syDone2026-10-202026-10-20Wins back 6 daysApprove a phased integration test plan instead of one big-bang test
Joud HammamiJoud HammamiQA & Testing SpecialistP-033joud.hammami@psa.gov.syOverdue3 days overdue2026-10-25Wins back 2 daysA weekly report on the plan to the National Projects Steering Committee
Eng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.syACT-0306In progressIn 6 days2026-11-03
Follow-up
The project’s readings after the plan was approved, with the PMO’s notes.
2026-10-27Dr. Reem Al-Qabbani42 days lateSPI 0.87
6 days won back since the first approval; replacing the engineers remains the condition for version 2
2026-10-13Dr. Reem Al-Qabbani45 days lateSPI 0.86
Three services moved to wave 2; the civil-registry environment is still down
2026-09-29Kinan Azzam48 days lateSPI 0.85
First reading after approval: no improvement yet, the vendor has not reinforced the team