RSK-0002Unified Government e-Services Platform

Shortage of integration and back-end engineers on the vendor team

16HighEscalatedMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

The vendor pulled two integration engineers onto another client, and back-end engineers are in high demand

Preventive controls

  • Formal letter to the vendor to restore the contractual staffing within 10 days
  • Change request to add integration capacity for four months
  • Apply the clause 14 staffing penalty if not resolved

1 / 3

Event

Shortage of integration and back-end engineers on the vendor team

16HighTrigger

The two replacements have not joined by 2026-11-05

Contingency

Borrow two engineers from the Authority’s Government Systems & Integration Directorate until the replacements join

Impact

Team velocity down 30%, with the civil-registry and interoperability interfaces and wave 1 services late

SYP 46.3M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
16High

Residual

5
4
3
2
1
1
2
3
4
5
6Low

Exposure

SYP 46.3M

Residual

⁦63⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 2 days ago

  1. Project manager

    Eng. Tarek Al-Mardini

    Currently followed up here
  2. Programme manager

    Current level

    Eng. Lina Al-Attar

    Automatically at 15 days unreviewed · in 13 days
  3. 3

    PMO director

    Dr. Reem Al-Qabbani

    Automatically at 20 days unreviewed · in 18 days
  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦2⁩ of ⁦3⁩ done
  • Formal letter to the vendor to restore the contractual staffing within 10 days

    Omar Al-NahhasOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.sy
    Done2026-10-202026-10-20
  • Change request to add integration capacity for four months

    Eng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.sy
    Done2026-10-262026-10-26
  • Apply the clause 14 staffing penalty if not resolved

    Omar Al-NahhasOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.sy
    Not startedIn 8 days2026-11-05

Trigger

The two replacements have not joined by 2026-11-05

Contingency

Borrow two engineers from the Authority’s Government Systems & Integration Directorate until the replacements join

Esc