CR-2026-012Unified Government e-Services Platform
Add vendor integration capacity for four months
Justification and the cost, schedule and risk impact, with a recommendation.
Impact analysis
Before and after — as it will show in the baseline if approved
Cost
+SYP 24.5MCurrent budgetSYP 2.2B
After the changeSYP 2.2B
+1.1%
Schedule
−12 d- Baseline finish2027-03-31
- New finish2027-03-19
Risk
−8Treats the staffing gap directly
Benefits
+2%Protects the official launch date
+2% of expected benefits
Reason for change
The vendor is short of integration engineers and the civil-registry and interoperability interfaces are late
Justification
Two engineers for four months win back 12 days and lower the project’s top risk
PMO recommendation
ApproveImpact analysis in progress at the national PMO
Approval workflow
Submitted
Eng. Tarek Al-Mardini
Done2026-10-26
PM review
Eng. Tarek Al-Mardini
Done2026-10-27
- 3
Impact analysis
Kinan Azzam
Now2026-10-31
- 4
Finance & procurement
Rasha Al-Mudarres
Later
- 5
Portfolio manager — capacity
Basel Al-Mahayni
Later
- 6
PMO approval
Dr. Reem Al-Qabbani
Later2026-10-29
- 7
Baseline updated
Eng. Tarek Al-Mardini
Later
Why this route
The route is built from the request’s kind and impact level under the approved authority matrix.
Impact levelMinorUp to SYP 25M and no extra days
- Impact SYP 24.5M and 0 days — «minor», so the PMO approves it without a committee.
- It has a financial link, so Finance & Procurement take part before the decision.
- It adds people, so the portfolio manager checks capacity.
Change committee vote
Members vote before or during the meeting; the decision is taken once quorum is met
- Dr. Ziad Al-AtassiDeputy President, Strategy & PerformanceDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syChairNot voted
- Dr. Reem Al-QabbaniDirector, National Project Management OfficeDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.syYouNot voted
- Omar Al-NahhasSenior Finance & Contracts SpecialistOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syNot voted
- Rasha Al-MudarresDirector General, Finance & ContractsRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.syNot voted
- Eng. Rita GhanemEnterprise ArchitectEng. Rita GhanemEnterprise ArchitectP-031rita.ghanem@psa.gov.syNot voted
- Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syNot voted
- Approve0
- Approve with conditions0
- Reject0
- Abstain0
4 short of quorum · Awaiting the change committee’s decision in meeting 42