CR-2026-012Unified Government e-Services Platform

Add vendor integration capacity for four months

ResourcesSubmittedImpact level: MinorIn 12 days2026-11-09

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SYP 24.5M

Current budgetSYP 2.2B

After the changeSYP 2.2B

+1.1%

Schedule

−⁦12⁩ d
  • Baseline finish2027-03-31
  • New finish2027-03-19

Benefits

+2%

Protects the official launch date

⁦+2⁩% of expected benefits

Reason for change

The vendor is short of integration engineers and the civil-registry and interoperability interfaces are late

Justification

Two engineers for four months win back 12 days and lower the project’s top risk

PMO recommendation

Approve

Impact analysis in progress at the national PMO

Approval workflow

  1. Submitted

    Eng. Tarek Al-Mardini

    Done2026-10-26

  2. PM review

    Eng. Tarek Al-Mardini

    Done2026-10-27

  3. 3

    Impact analysis

    Kinan Azzam

    Now2026-10-31

  4. 4

    Finance & procurement

    Rasha Al-Mudarres

    Later

  5. 5

    Portfolio manager — capacity

    Basel Al-Mahayni

    Later

  6. 6

    PMO approval

    Dr. Reem Al-Qabbani

    Later2026-10-29

  7. 7

    Baseline updated

    Eng. Tarek Al-Mardini

    Later

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelMinorUp to SYP 25M and no extra days

  • Impact SYP 24.5M and 0 days — «minor», so the PMO approves it without a committee.
  • It has a financial link, so Finance & Procurement take part before the decision.
  • It adds people, so the portfolio manager checks capacity.

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

Change Committee — meeting 4229 October 2026 13:00Meeting room 3 — fifth floor
  • Dr. Ziad Al-AtassiDeputy President, Strategy & PerformanceDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syChairNot voted
  • Dr. Reem Al-QabbaniDirector, National Project Management OfficeDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.syYouNot voted
  • Omar Al-NahhasSenior Finance & Contracts SpecialistOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syNot voted
  • Rasha Al-MudarresDirector General, Finance & ContractsRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.syNot voted
  • Eng. Rita GhanemEnterprise ArchitectEng. Rita GhanemEnterprise ArchitectP-031rita.ghanem@psa.gov.syNot voted
  • Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syNot voted
0/6⁦4⁩ short of quorum
  • Approve0
  • Approve with conditions0
  • Reject0
  • Abstain0

⁦4⁩ short of quorum · Awaiting the change committee’s decision in meeting ⁦42⁩