Proposal & feasibility study — unified e-services platform

ConfidentialApprovedV2

The economic and technical case for the Unified Government e-Services Platform: three options, NPV, payback and a sensitivity analysis.

More
Showing version:

Confidential

Syrian Arab Republic

Planning and Statistics Authority

National Project Management Office (PMO)

Code
DOC-0202
Version
V2
Date
2024-09-15

Proposal & feasibility study — unified e-services platform

Unified Government e-Services Platform

⁦1⁩. Problem & opportunity

This case addresses the need for Unified Government e-Services Platform and compares three options on cost, value and risk.

Project
Unified Government e-Services Platform (⁦PRJ-2026-014⁩)
Project manager
Eng. Tarek Al-Mardini
Budget
⁦SYP 2⁩.⁦16bn⁩
Progress
⁦58% actual against 67% planned⁩
Forecast finish
⁦2027-05-12⁩

⁦2⁩. Options

OptionCostNPVRecommendation
Do nothing—NegativeRejected
Partial⁦SYP 1⁩.⁦30bn⁩LowFallback
Full solution⁦SYP 2⁩.⁦16bn⁩HighestRecommended

⁦3⁩. Sensitivity

⁦NPV stays positive up to an 18% cost overrun or a full year⁩’s delay in benefits.

Prepared by

Basel Al-Mahayni

Project manager

Eng. Tarek Al-Mardini
Issued from Munjaz — valid only once approved electronically1 / 1