Late civil-registry and interoperability-framework readiness delays both the platform and the app
PRK-01-1·Mitigate·Eng. Lina Al-Attar
Programme · PG-01 · Digital Government Services & Data Portfolio
One citizen journey across the unified e-services platform, the app, digital signatures and e-litigation.
incl. SYP 100M programme reserve
65% of budget
Estimate at completion
Planned 78%
Cost performance index 0.98
Manager
Eng. Lina Al-Attar
Head of the Unified Government e-Services Platform & Programme Manager, Government e-Services
Sponsor
Eng. Khaled Al-Kayyali
Deputy President, Digital Transformation
Projects
4 projects
2024-04-07 — 2027-05-12
On track 3At risk 1
What the programme must achieve, and the strategic objectives it serves.
One citizen journey for government services on the unified platform and the app, with identity checked against the civil registry
Lift government services fully available online from 55% to 80% by the end of 2027
Cut in-person visits to the citizen service centres by 40% by moving them to digital channels
From baseline to target
Citizen satisfaction with digital services
by 2027Average time to complete transactions that need review
by 2027Running savings at the citizen service centres
by 2028One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
The digital-signature and document-verification engine is reused inside the unified platform
Electronic judicial notices are linked to the citizen’s account on the unified platform after launch
Critical
The mobile app consumes the unified platform’s APIs and the civil-registry integration
Risks that hit more than one project, managed at programme level.
Late civil-registry and interoperability-framework readiness delays both the platform and the app
PRK-01-1·Mitigate·Eng. Lina Al-Attar
One vendor integration team serves three projects in the programme
PRK-01-2·Escalate·Eng. Lina Al-Attar
10 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 2 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 3 · Medium | 2 · Medium | 0 · High |
| 2 | 0 · Low | 0 · Low | 2 · Low | 1 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Citizen satisfaction with digital government services
74%
0
Target 85%87%
Government services fully available online
69%
+1
Target 80%86%
Transactions completed without a visit
58%
+1
Target 60%97%
Transactions completed at citizen service centres per month
4.1thousand transactions
0
Target 4.591%
Power against interest; click a person to see their role.
Keep satisfied2
Manage closely3
Monitor0
Keep informed1
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Committees
Monthly · Quorum 5
Members
6 members
Fortnightly · Quorum 4
Members
7 members
Weekly · Quorum 4
Members
5 members
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| e-Litigation & Judicial Notification Platform — Release 2PRJ-2026-008 | Kinan Azzam | 4Execution | On track | 91% | SYP460M | SYP451M−2.0% | 1.01Schedule performance index · 1.01 | 1.02Cost performance index · 1.02 |
| Unified Government e-Services PlatformPRJ-2026-014 | Eng. Tarek Al-Mardini | 4Execution | At risk | 58% | SYP2.2B | SYP2.3B+4.2% | 0.87Schedule performance index · 0.87 | 0.96Cost performance index · 0.96 |
| Government Services Mobile App — New ReleasePRJ-2026-015 | Kinan Azzam | 4Execution | On track | 64% | SYP315M | SYP302.9M−3.8% | 1.02Schedule performance index · 1.02 | 1.04Cost performance index · 1.04 |
| Digital Signature & e-Verification of Government Documents — Phase 1PRJ-2026-031 | Kinan Azzam | 5Closure | On track | 100% | SYP205M | SYP199M−2.9% | 1.00Schedule performance index · 1.00 | 1.03Cost performance index · 1.03 |
| Total · 4 | SYP3.1B | SYP3.2B |
SYP 3.1B
Budget
| Category | Value | Share |
|---|---|---|
| e-Litigation & Judicial Notification Platform — Release 2 | SYP 460M | 15% |
| Unified Government e-Services Platform | SYP 2.2B | 69% |
| Government Services Mobile App — New Release | SYP 315M | 10% |
| Digital Signature & e-Verification of Government Documents — Phase 1 | SYP 205M | 7% |
| Total | SYP 3.1B | 100% |