Portfolio · PF-DT

Digital Government Services & Data Portfolio

At risk

The unified e-services platform and app, digital signatures and e-litigation, the national indicators portal, the plan tracker and the national development forum.

What-if scenarios
Approved budget
SYP 5.2B

incl. SYP 242.5M unallocated reserve

Actual spend
SYP 2.5B

⁦47%⁩ of budget

EAC
SYP 5.1B−2.9%

Estimate at completion

Expected value
SYP 16B

⁦14%⁩ realised

Health score
74−5

was ⁦79⁩ in May

Manager

Basel Al-Mahayni

Director General, Digital Government Services & Portfolio Manager, Digital Government Services & Data

Owner

Eng. Khaled Al-Kayyali

Deputy President, Digital Transformation

AI insight

⁦2⁩ projects in this portfolio are pulling its health down

Most of it comes from “Unified Government e-Services Platform” (SPI ⁦0.87⁩) and “National Statistical Indicators & Open Data Portal” (SPI ⁦0.89⁩). Fixing those two lifts the portfolio towards ⁦83⁩ within two quarters.

Confidence⁦81%⁩

Weighted portfolio progress

Σ each project’s relative weight × its actual progress, under the approved project weight model

What each project adds to portfolio progress

The project’s weight from the model, its relative weight among the portfolio’s counted projects, and what it adds

ProjectProject weightRelative weightActual progressWeight × progress
Unified Government e-Services Platform88.0⁦21.8%⁩⁦58%⁩⁦12.6%⁩
National Statistical Indicators & Open Data Portal70.0⁦17.3%⁩⁦62%⁩⁦10.7%⁩
Medium-Term Plan Implementation Tracker (ministries & governorates)66.0⁦16.3%⁩⁦1%⁩⁦0.2%⁩
e-Litigation & Judicial Notification Platform — Release 263.0⁦15.6%⁩⁦91%⁩⁦14.2%⁩
Government Services Mobile App — New Release63.0⁦15.6%⁩⁦64%⁩⁦10.0%⁩
Digital Signature & e-Verification of Government Documents — Phase 154.0⁦13.4%⁩⁦100%⁩⁦13.4%⁩
National Development & Reconstruction Forum 2027Left out — proposed59.0—⁦0%⁩—
Portfolio progress⁦61.1%⁩

How it is computed

⁦61.1%⁩

Portfolio progress = Σ (project relative weight × actual progress). Relative weight = the project’s weight ÷ the weights of the counted projects, so they add up to 100%.

  • · Proposed and cancelled projects never count.
  • · Left out of this portfolio now: ⁦1⁩
  • · For comparison: weighting by budget alone gives ⁦48.6%⁩

Suspended projects

Open the project weight model

Portfolio health & performance

The health score from eight weighted dimensions, and the schedule and cost indices over six months.

Health-score breakdown

Score × weight = points

74At risk
DimensionScoreWeightPoints
Schedule68⁦20%⁩13.6
Cost84⁦20%⁩16.8
Risk62⁦15%⁩9.3
Scope80⁦10%⁩8.0
Quality82⁦10%⁩8.2
Resources66⁦10%⁩6.6
Stakeholders78⁦5%⁩3.9
Benefits76⁦10%⁩7.6
Total74

Health-score trend

May – October 2026

7974

Financial & schedule performance

May – October 2026

Both indices over time

  • Schedule performance index
  • Cost performance index

Portfolio project map

risk across, strategic value up, bubble size by budget. Click a bubble for a quick look at the project.

Portfolio project map

  • On track
  • At risk
Approved budget · SYP 2.2B

Funding priority order

Rank the projects for funding; your order is kept and goes to the 2027 planning cycle.

  1. 1Unified Government e-Services PlatformPRJ-2026-014·Priority score 91At risk
  2. 2e-Litigation & Judicial Notification Platform — Release 2PRJ-2026-008·Priority score 80On track
  3. 3Government Services Mobile App — New ReleasePRJ-2026-015·Priority score 78On track
  4. 4Medium-Term Plan Implementation Tracker (ministries & governorates)PRJ-2026-023·Priority score 76On track
  5. 5National Statistical Indicators & Open Data PortalPRJ-2026-016·Priority score 72At risk
  6. 6National Development & Reconstruction Forum 2027PRJ-2026-035·Priority score 52On track

Portfolio priorities 2026–2027

  • Launch the unified e-services platform by Q2 2027The portfolio’s critical path — the government services app and the e-litigation link to the civil registry depend on it.
  • Lift government services fully available online to 80%Tied directly to the citizen digital-satisfaction KPI that is behind target.
  • Publish the national indicators and medium-term plan tracking on governed dataConditional on the ministries’ and governorates’ data being catalogued in the national indicators portal.

Objectives & KPIs

Why the portfolio exists: the strategic objectives it serves and the KPIs its projects move.

Budget & value

Where the budget goes, why the forecast differs from it, and the value it returns.

From approved budget to estimate at completion

Each programme’s gap between its projects’ budget and their forecast

From approved budget to estimate at completion
  • Total
  • Increase
  • Decrease
From approved budget to estimate at completion
CategoryChangeRunning total
Approved budgetSYP 5.2BSYP 5.2B
Unallocated reserve−SYP 242.5MSYP 5B
Government e-Services Programme+SYP 62.9MSYP 5B
National Data & Plan Follow-up Programme+SYP 28.3MSYP 5.1B
Projects outside a programmeSYP 0SYP 5.1B
Estimate at completionSYP 5.1BSYP 5.1B

Budget use

SYP2.5B/ SYP5.2BSYP151.3Mprojected saving(⁦2.9%⁩)
Actual spend
SYP2.5B
Committed
SYP3.1B
Approved budget
SYP5.2B
Estimate at completion
SYP5.1B

Expected-value mix

Expected-value mix

SYP 16B

Expected value

  • Time savedSYP 5.4B⁦34%⁩
  • Beneficiary satisfactionSYP 4.2B⁦26%⁩
  • Cost savingSYP 3.5B⁦22%⁩
  • RevenueSYP 2.9B⁦18%⁩
Expected-value mix
CategoryValueShare
Time savedSYP 5.4B⁦34%⁩
Beneficiary satisfactionSYP 4.2B⁦26%⁩
Cost savingSYP 3.5B⁦22%⁩
RevenueSYP 2.9B⁦18%⁩
TotalSYP 16B⁦100%⁩

SYP 2.3B

Expected value SYP 16B

⁦78%⁩ of what was planned by today

Programmes & projects

A programme’s performance is computed from its projects. Click a project for a quick look.

⁦7⁩ results
Export CSV
Unified Government e-Services PlatformPRJ-2026-014PG-014ExecutionAt risk⁦58%⁩⁦21.8%⁩P1P1 · Top priority — score ⁦91⁩ of 100SYP2.2BSYP2.3B⁦+4.2%⁩0.87Schedule performance index · 0.870.96Cost performance index · 0.96Risk score · Weak
Medium-Term Plan Implementation Tracker (ministries & governorates)PRJ-2026-023PG-022InitiationOn track⁦1%⁩⁦16.3%⁩P1P1 · Top priority — score ⁦76⁩ of 100SYP700MSYP700M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00Risk score · Good
National Development & Reconstruction Forum 2027PRJ-2026-035—1Pre-startOn track⁦0%⁩—P3P3 · Medium priority — score ⁦52⁩ of 100SYP600MSYP600M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00Risk score · Good
National Statistical Indicators & Open Data PortalPRJ-2026-016PG-024ExecutionAt risk⁦62%⁩⁦17.3%⁩P2P2 · High priority — score ⁦72⁩ of 100SYP537.5MSYP565.8M⁦+5.3%⁩0.89Schedule performance index · 0.890.95Cost performance index · 0.95Risk score · Fair
e-Litigation & Judicial Notification Platform — Release 2PRJ-2026-008PG-014ExecutionOn track⁦91%⁩⁦15.6%⁩P1P1 · Top priority — score ⁦80⁩ of 100SYP460MSYP451M⁦−2.0%⁩1.01Schedule performance index · 1.011.02Cost performance index · 1.02Risk score · Good
Government Services Mobile App — New ReleasePRJ-2026-015PG-014ExecutionOn track⁦64%⁩⁦15.6%⁩P1P1 · Top priority — score ⁦78⁩ of 100SYP315MSYP302.9M⁦−3.8%⁩1.02Schedule performance index · 1.021.04Cost performance index · 1.04Risk score · Good
Digital Signature & e-Verification of Government Documents — Phase 1PRJ-2026-031PG-015ClosureOn track⁦100%⁩⁦13.4%⁩P1P1 · Top priority — score ⁦75⁩ of 100SYP205MSYP199M⁦−2.9%⁩1.00Schedule performance index · 1.001.03Cost performance index · 1.03Risk score · Excellent
Total · 7SYP5BSYP5.1B
⁦1⁩–⁦7⁩ of ⁦7⁩

Portfolio risks

Open threats across the portfolio’s projects. Click a cell on the map to filter the list.

Open-risk heat map

11 risks

Open-risk heat map
  • Critical0
  • High2
  • Medium7
  • Low2
  • Risks 11
Probability
5
4
3
2
1
12345

Impact

Open-risk heat map
Probability \ Impact12345
50 · Low0 · Medium0 · High0 · Critical0 · Critical
40 · Low0 · Medium0 · Medium2 · High0 · Critical
30 · Low0 · Low4 · Medium2 · Medium0 · High
20 · Low0 · Low2 · Low1 · Medium0 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Latest on this portfolio

26 October 2026

  1. Gate decision: National Projects Steering Committee Conditional Go DEC-2026-042Plan tracker passes into planning with conditions

    2026-10-26 10:00

15 September 2026

  1. Gate decision: National Projects Steering Committee Conditional Go DEC-2026-031Corrective plan approved for the unified government e-services platform

    2026-09-15 10:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close