Programme · PG-02 · Digital Government Services & Data Portfolio

National Data & Plan Follow-up Programme

At risk

The national indicators and open-data portal, and the medium-term plan implementation tracker.

Approved budget
SYP 1.3B

incl. SYP 62.5M programme reserve

Actual spend
SYP 357.8M

⁦28%⁩ of budget

EAC
SYP 1.3B+2.3%

Estimate at completion

Progress
⁦32%⁩

Planned ⁦37%⁩

Schedule performance index
0.95

Cost performance index 0.98

Manager

Razan Al-Rifai

Director, Data & AI

Sponsor

Eng. Mustafa Al-Awa

Deputy President, Planning

Projects

2 projects

2025-08-03 — 2027-12-31

On track 1At risk 1

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    Document 60% of the ministries’ and governorates’ core statistical data in an approved catalogue

  2. 2

    Publish 24 bulletins, reports and indicators on the national indicators portal by the end of 2027

  3. 3

    Follow every medium-term plan project until the delivering body completes it

Programme benefits

From baseline to target

  • Core statistical data documented

    by ⁦2027⁩
    Baseline 15Current 41 %Target 60
  • AI use cases in production

    by ⁦2027⁩
    Baseline 1Current 6 casesTarget 8

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
202520262027
2027-01-18
2027-12-31

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • Critical

    The plan tracker needs documented master data for governorates, sectors and delivering bodies

Shared risks

Risks that hit more than one project, managed at programme level.

12

Late ministry-data cataloguing delays linking the plan tracker to the delivering bodies

PRK-02-1·Mitigate·Razan Al-Rifai

Affects

Open risks in the programme’s projects

1 risk

Open risks in the programme’s projects
  • Critical0
  • High0
  • Medium1
  • Low0
  • Risks 1
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High0 · Critical0 · Critical
40 · Low0 · Medium0 · Medium0 · High0 · Critical
30 · Low0 · Low1 · Medium0 · Medium0 · High
20 · Low0 · Low0 · Low0 · Medium0 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied0

Manage closely4

Monitor0

Keep informed0

Eng. Mustafa Al-AwaManage closelyRazan Al-RifaiManage closelyIman Al-JasemManage closelyEng. Hussam ZeidanManage closely

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

Committees

National Projects Steering Committee

Monthly · Quorum ⁦5⁩

Dr. Ziad Al-Atassi · Deputy President, Strategy & PerformanceEng. Abdulrahman Al-Kilani · Deputy President, Development Projects Follow-upEng. Khaled Al-Kayyali · Deputy President, Digital Transformation
Chair: Dr. Samer Al-DaqqarNext meeting 2026-11-03
Project Approval Committee

Fortnightly · Quorum ⁦4⁩

Basel Al-Mahayni · Director General, Digital Government Services & Portfolio Manager, Digital Government Services & DataDr. Mais Al-Sibai · Director General, Strategy & National ProjectsNizar Abu Fakhr · Head, Monitoring, Evaluation & Performance
Chair: Dr. Reem Al-QabbaniNext meeting 2026-11-04

Programme projects

The programme’s performance is computed from these projects.

⁦2⁩ results
Export CSV
Manager
National Statistical Indicators & Open Data PortalPRJ-2026-016Razan Al-Rifai4ExecutionAt risk⁦62%⁩SYP537.5MSYP565.8M⁦+5.3%⁩0.89Schedule performance index · 0.890.95Cost performance index · 0.95
Medium-Term Plan Implementation Tracker (ministries & governorates)PRJ-2026-023Razan Al-Rifai2InitiationOn track⁦1%⁩SYP700MSYP700M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Total · 2SYP1.2BSYP1.3B
⁦1⁩–⁦2⁩ of ⁦2⁩

Budget shares

Budget shares

SYP 1.2B

Budget

  • National Statistical Indicators & Open Data PortalSYP 537.5M⁦43%⁩
  • Medium-Term Plan Implementation Tracker (ministries & governorates)SYP 700M⁦57%⁩
Budget shares
CategoryValueShare
National Statistical Indicators & Open Data PortalSYP 537.5M⁦43%⁩
Medium-Term Plan Implementation Tracker (ministries & governorates)SYP 700M⁦57%⁩
TotalSYP 1.2B⁦100%⁩