Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-015On track4ExecutionScrumIn progressDelivered by:Ministry of Communications and Information Technology

Government Services Mobile App — New Release

Add to watchlist

The new release of the government services app: the most-used services, request tracking, notifications and bank e-payment.

Budget (BAC)

SYP 315M

Actual cost

SYP 193.8M

⁦62%⁩ of budget

Progress

⁦64%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 302.9M

SPI · CPI

1.02Schedule performance index · 1.021.04Cost performance index · 1.04

Forecast finish

⁦2027-01-28⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+4

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦64% done against 63% planned⁩.

⁦SPI 1⁩.⁦02⁩, ⁦CPI 1⁩.⁦04⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Governance & Digital TransformationSO-5.1Integrated digital government services for citizens

Main initiative

SI-5.1.1Unified government services

Contribution to the initiative⁦12%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

No secondary links

Annual work-plan line
WP-2025-015
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦64%⁩

Awaiting acceptance ⁦10%⁩

Not handed in ⁦26%⁩

6 deliverables accepted

  • Release 1⁦16%⁩
  • Release 2⁦16%⁩
  • Business requirements⁦11%⁩
  • Solution design⁦11%⁩
  • Project plan & baseline⁦5%⁩
  • Monitoring & reporting⁦5%⁩

1 deliverable under inspection or acceptance

  • Integrations⁦10%⁩

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦87%⁩ of budget

SYP193.8M/ SYP315MSYP12.1Mprojected saving(⁦3.8%⁩)
Actual spend
SYP193.8M
Committed
SYP272.5M
Approved budget
SYP315M
Estimate at completion
SYP302.9M

Next milestones

  • Provisional acceptance⁦2026-12-21⁩was ⁦2026-12-23⁩On track
  • Closure⁦2027-01-28⁩was ⁦2027-01-31⁩On track

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Risks & impediments

0 open risks, exposure SYP 0

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium0
  • Low0

Top risks

  • No open risks

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦6⁩ of ⁦11⁩ approved

  • Project plan & baseline015-D1 · V1 · CRT-015-01⁦5%⁩Kinan Azzam2025-12-112025-12-11Approved
  • Monitoring & reporting015-D2 · V1 · CRT-015-02⁦5%⁩Basel Al-Mahayni2026-01-212026-01-21Approved
  • Business requirements015-D3 · V1 · CRT-015-03⁦11%⁩Basel Al-Mahayni2026-03-042026-03-04Approved
  • Solution design015-D4 · V1 · CRT-015-04⁦11%⁩Eng. Khaled Al-Kayyali2026-04-152026-04-15Approved
  • Release 1015-D5 · V1 · CRT-015-05⁦16%⁩Eng. Khaled Al-Kayyali2026-05-262026-05-26Approved
  • Release 2015-D6 · V1 · CRT-015-06⁦16%⁩Kinan Azzam2026-07-072026-07-07Approved
  • Integrations015-D7 · V1⁦10%⁩Basel Al-Mahayni72 days overdue2026-08-17In review
  • System testing015-D8 · V0⁦7%⁩Kinan Azzam30 days overdue2026-09-28Draft
  • User acceptance testing015-D9 · V0⁦7%⁩Basel Al-MahayniIn 12 days2026-11-09Draft
  • Training & change015-D10 · V0⁦6%⁩Basel Al-MahayniIn 53 days2026-12-20Draft
  • Go-live & handover015-D11 · V0⁦6%⁩Eng. Khaled Al-KayyaliIn 95 days2027-01-31Draft

Team, contracts & documents

Team

7 members

Kinan Azzam · Senior Digital Delivery Consultant — National PMOEng. Lina Al-Attar · Head of the Unified Government e-Services Platform & Programme Manager, Government e-ServicesIbrahim Al-Saeed · Director General, Government Services in the GovernoratesJoud Hammami · QA & Testing SpecialistHamza Al-Hussein · Senior Software Engineer – IntegrationHiba Al-Shami · Senior Business Analyst — Government Services
  • Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOProject managerP-041kinan.azzam@psa.gov.sy⁦40%⁩
  • Eng. Lina Al-AttarEng. Lina Al-AttarHead of the Unified Government e-Services Platform & Programme Manager, Government e-ServicesProgramme oversight, mobile appP-004lina.alattar@psa.gov.sy⁦15%⁩
  • Ibrahim Al-SaeedIbrahim Al-SaeedDirector General, Government Services in the GovernoratesProject ownerP-046ibrahim.alsaeed@psa.gov.sy⁦5%⁩
  • Joud HammamiJoud HammamiQA & Testing SpecialistApp testingP-033joud.hammami@psa.gov.sy⁦40%⁩
  • Hamza Al-HusseinHamza Al-HusseinSenior Software Engineer – IntegrationApp APIs to the unified platformP-030hamza.alhussein@psa.gov.sy⁦35%⁩
  • Hiba Al-ShamiHiba Al-ShamiSenior Business Analyst — Government ServicesApp service requirementsP-006hiba.alshami@psa.gov.sy⁦25%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close