PRJ-2026-015On track4ExecutionScrumIn progressDelivered by:Ministry of Communications and Information Technology
Government Services Mobile App — New Release
Add to watchlistThe new release of the government services app: the most-used services, request tracking, notifications and bank e-payment.
Project managerKinan AzzamProject sponsorEng. Khaled Al-KayyaliProgrammeGovernment e-Services Programme
Budget (BAC)
SYP 315M
Actual cost
SYP 193.8M
62% of budget
Progress
64%Awaiting acceptance 10%
Estimate at completion
SYP 302.9M
SPI · CPI
1.02Schedule performance index · 1.021.04Cost performance index · 1.04
Forecast finish
2027-01-28
On baseline
ExecutionStage 4 of 5
Next gate:Closure23 December 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Periodic update cards
| Period | Status | Progress | Current step | Date |
|---|---|---|---|---|
| October 2026UPD-015-2026-10 | Draft | 64% | — | 2026-10-26 |
| September 2026UPD-015-2026-09 | Approved | 60% | — | 2026-10-02 |
| August 2026UPD-015-2026-08 | Approved | 57% | — | 2026-09-02 |