PRJ-2026-015On track4ExecutionScrumIn progressDelivered by:Ministry of Communications and Information Technology

Government Services Mobile App — New Release

Add to watchlist

The new release of the government services app: the most-used services, request tracking, notifications and bank e-payment.

Budget (BAC)

SYP 315M

Actual cost

SYP 193.8M

⁦62%⁩ of budget

Progress

⁦64%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 302.9M

SPI · CPI

1.02Schedule performance index · 1.021.04Cost performance index · 1.04

Forecast finish

⁦2027-01-28⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SYP 315M split into spent, committed and left, with the estimate at completion

EAC SYP 302.9M
Revised request SYP 315M
  • Actual spendSYP 193.8M
  • Committed, not spentSYP 78.7M
  • Allotted, uncommittedSYP 33.1M
  • Contingency availableSYP 9.5M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SYP 305M
Original budgetwhen the first baseline was approved
SYP 315M
Approved budgetafter approved change requests
SYP 315M
Current budgetavailable to spend now
SYP 315M
Revised budgetif the pending changes are approved
SYP 315M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SYP 272.5M
Contracts1 active contract
SYP 245M
Purchase orders⁦2⁩ orders
SYP 27.5M
Remaining budgetapproved less actual
SYP 121.2M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SYP 193.8M
Accrualswork done, not yet invoiced
SYP 7.8M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SYP 302.9M
ContingencySYP 6.3M drawn of SYP 15.8M
SYP 9.5M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSYP 305M
ApprovedSYP 315M
Estimate at completionSYP 302.9M
Approved is SYP 10M (⁦3.3%⁩) above the estimate
The estimate at completion is SYP 2.1M (⁦0.7%⁩) below the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-07-22⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-41015
  • WBS elements⁦5⁩ elements · P-2026-015.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦8⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SYP 6.3M drawn of SYP 15.8M

  • Covering realised delivery risks⁦2026-08-29⁩SYP 6.3M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSYP MCommittedSYP MActualSYP MEACSYP MVarianceSYP MConsumption
1Management & governance24.4424.3924.2624.43⁦+0.01⁩
2Analysis & design51.9451.8351.5451.92⁦+0.03⁩
3Build122.22120.98118.05121.94⁦+0.28⁩
4Testing & acceptance61.1143.030.0057.07⁦+4.04⁩
5Launch & handover45.8332.270.0042.80⁦+3.03⁩
Unallocated contingency9.450.000.004.73⁦+4.73⁩
Total315.00272.50193.85302.89⁦+12.12⁩

Budget split

WBS

SYP 315M

Budget

  • Management & governanceSYP 24.4M⁦8%⁩
  • Analysis & designSYP 51.9M⁦16%⁩
  • BuildSYP 122.2M⁦39%⁩
  • Testing & acceptanceSYP 61.1M⁦19%⁩
  • Launch & handoverSYP 45.8M⁦15%⁩
  • Unallocated contingencySYP 9.5M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SYP millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-07-27⁩+177

SPI(t) ⁦0.73⁩ against the approved finish ⁦2027-01-31⁩

Planned valuePV
SYP 285.9M
The value of the work that should be done by today.
PV
Earned valueEV
SYP 201.6M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SYP 193.8M
What has actually been spent on the work done.
AC
Budget at completionBAC
SYP 315M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+7.75⁩ SYP M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−84.33⁩ SYP M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.04
Value produced per pound spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.71
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SYP 302.9M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SYP 109M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+12.12⁩ SYP M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.94
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSYP 302.9M
  • If the rest goes to planSYP 307.2M
  • At cost and schedule performanceSYP 348.5M
  • The PM’s bottom-up estimateSYP 302.9M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SYP 302.9M

Variance at completion: ⁦+12.12⁩ SYP M