Government Services Mobile App — New Release
Add to watchlistThe new release of the government services app: the most-used services, request tracking, notifications and bank e-payment.
Budget (BAC)
Actual cost
62% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure23 December 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started
Scope statementRequired at this stage
What the project delivers, what it does not, and when a deliverable counts as accepted.
The new release of the government services app: the most-used services, request tracking, notifications and bank e-payment.
In scope
- The new release of the government services app: the most-used services, request tracking, notifications and bank e-payment.
- Identity checks against the civil registry
- Integration with internal systems
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the project owner
- Main deliverable — final stageMeets the approved specification, signed off by the project owner
Scope baselineRequired at this stage
Every approved change creates a new baseline
- 1
SB-1Current2025-10-28
Baseline approved at the planning gate
BudgetSYP315MFinish2027-01-31
Requirements registerRequired at this stage
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional2
- Technical1
- Regulatory1
- Security1
Fully traced
100%
6/6 · linked to a deliverable, task and test
Test passed
17%
1/6 · test result is a pass
Accepted
17%
1/6 · signed off by the business owner
Display options
| REQ-015-01 | An end-to-end digital journey, no walk-in | Business | Must | Approved | Basel Al-MahayniBasel Al-MahayniDirector General, Digital Government Services & Portfolio Manager, Digital Government Services & DataP-003basel.almahayni@psa.gov.sy | SB-1 | |
| REQ-015-02 | Identity checks against the civil registry | Functional | Must | Approved | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | SB-1 | |
| REQ-015-03 | A user dashboard | Functional | Must | In progress | Basel Al-MahayniBasel Al-MahayniDirector General, Digital Government Services & Portfolio Manager, Digital Government Services & DataP-003basel.almahayni@psa.gov.sy | SB-1 | |
| REQ-015-04 | Integration with internal systems | Technical | Should | In progress | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | SB-1 | |
| REQ-015-05 | WCAG 2.1 accessibility | Regulatory | Could | Approved | Basel Al-MahayniBasel Al-MahayniDirector General, Digital Government Services & Portfolio Manager, Digital Government Services & DataP-003basel.almahayni@psa.gov.sy | SB-1 | |
| REQ-015-06 | National cybersecurity controls | Security | Could | In progress | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy | SB-1 |
Traceability matrixRequired at this stage
Requirement → deliverable → task → test → acceptance. No requirement has a gap.